Birla Estates has three project names in Gurgaon on the HRERA Gurugram register: Birla Arika in Sectors 31–32A (two phases), Birla Pravaah in Sector 71, and Birla Navya in Sector 63A on Golf Course Extension Road (three phases under construction, two completed). The six live registrations carry HRERA completion dates from 31 December 2026 (Navya Anaika) to 9 July 2033 (Arika Phase 2). The only 2026 launch was Arika Phase 2, where 152 of 156 homes were booked for over ₹1,600 crore within a month, per a 7 April 2026 report.
Updated 20 November 2026. We read the HRERA Gurugram register and the REP-I filing of every live Birla registration, Birla Estates’ NCR page, and dated reports of the company’s booking disclosures. Navya is registered to Avarna Projects LLP, not to Birla Estates, so a search by the brand name alone misses it.
Birla Estates Gurgaon projects at a glance (HRERA)
Project — Sector — HRERA promoter — RERA no. — Homes (REP-I) — HRERA completion. Ordered by completion date.
- Birla Navya Anaika — Sector 63A — Avarna Projects LLP — RERA-GRG-1012-2022 — 120 — 31 Dec 2026
- Birla Navya Avik Phase 1 — Sector 63A — Avarna Projects LLP — RERA-GRG-1233-2022 — 92 — 30 Apr 2027
- Birla Navya Avik Phase 2 — Sector 63A — Avarna Projects LLP — RERA-GRG-1829-2024 — 141 — 30 Apr 2030
- Birla Arika (Phase 1) — Sectors 31–32A — Birla Estates Pvt Ltd — RERA-GRG-1823-2024 — 322 apartments — 9 Dec 2031
- Birla Pravaah — Sector 71 — Birla Estates Pvt Ltd — RERA-GRG-2071-2025 — 492 apartments — 31 Mar 2032
- Birla Arika Phase 2 — Sectors 31–32A — Birla Estates Pvt Ltd — RERA-GRG-2142-2025 — 234 — 9 Jul 2033
Birla Arika Phase 2, Sector 31
- Builder and promoter: Birla Estates Private Limited.
- RERA no.: RERA-GRG-2142-2025, registration GGM/1044/776/2026/16 dated 25 February 2026.
- Land: 1.53 acres within a 13.275-acre licence shared with Phase 1.
- Homes: 234 apartments of 215.45 to 218.89 sq m carpet, about 2,319 to 2,356 sq ft (our conversion).
- Estimated project cost filed: ₹2,287.83 crore; construction start given as 10 March 2026.
- HRERA completion: 9 July 2033 on the register. The REP-I form shows a likely completion of 9 October 2033; the register date is the one to quote in an agreement.
- Launch result: 152 of 156 homes released were booked within a month, over ₹1,600 crore (Free Press Journal, 7 April 2026).
- Our page: Birla Arika. Our earlier deep dive: Birla Arika Sector 31 Gurugram: Price, RERA, Possession 2026
Birla Arika (Phase 1), Sectors 31–32A
- RERA no.: RERA-GRG-1823-2024, registration GGM/914/646/2025/17 dated 20 February 2025.
- Land: 11.745 acres of the 13.275-acre licence.
- Homes: 322 apartments of 215.45 to 261.56 sq m carpet (about 2,319 to 2,815 sq ft), plus 64 small units of 18.6 to 21 sq m listed separately in the filing.
- Estimated project cost: ₹2,603.25 crore; construction start 10 March 2025.
- HRERA completion: 9 December 2031.
- Sales: about ₹3,000 crore for Phase 1, as cited in the 7 April 2026 Free Press Journal report.
- Birla Estates’ NCR page lists Arika as 4 BHK, two residences per floor, four clubhouses and 75% open green space.
Birla Pravaah, Sector 71
- RERA no.: RERA-GRG-2071-2025, registration GGM/1006/738/2025/109 dated 6 November 2025.
- Land: 5.075 acres, off the Southern Peripheral Road.
- Homes: 492 apartments, mostly 98.34 sq m (about 1,059 sq ft) and 120.73 sq m (about 1,300 sq ft) carpet, with a few from about 843 to 2,406 sq ft; 95 small units are listed separately.
- Configurations on Birla Estates’ page: 3 BHK and 3 BHK + utility.
- Estimated project cost: ₹1,284.31 crore; construction start 1 May 2026.
- HRERA completion: 31 March 2032.
- Launch result: all 492 homes sold within 24 hours for over ₹1,800 crore, per a regulatory filing by Aditya Birla Real Estate (PTI, 9 December 2025).
- Our page: Birla Pravaah. Sector guide: Sector 71 Gurgaon, Gurgaon
Birla Navya, Sector 63A: phases and possession dates
Birla Estates’ NCR page describes Navya as a township of floor residences on 47-plus acres across five pockets, with more than 450 families already moved into earlier phases. Portals quote anywhere from 10 to 73 acres; the developer’s own 47-plus acres is the figure to use. The REP-I filings name the promoter as Avarna Projects LLP, whose partners are Birla Estates Private Limited and Anant Raj Limited.
- Navya Anaika: RERA-GRG-1012-2022, registered 27 July 2022; about 2.06 acres; 120 low-rise apartments of 127.28 to 146.04 sq m carpet (about 1,370 to 1,572 sq ft); HRERA completion 31 December 2026.
- Navya Avik Phase 1: RERA-GRG-1233-2022, registered 23 January 2023; 1.61 acres; 92 apartments in 23 low-rise buildings, total carpet 13,475 sq m (about 1,577 sq ft per home on average, our arithmetic); HRERA completion 30 April 2027.
- Navya Avik Phase 2: RERA-GRG-1829-2024, registered 5 February 2025; about 2.67 acres; 141 apartments of about 1,161 to 2,481 sq ft carpet; construction start 1 April 2025; HRERA completion 30 April 2030.
- Navya Drisha 1A (RERA-GRG-505-2019) and Drisha 1B (RERA-GRG-1011-2022): completed phases with an OC/CC/PCC record listed on the HRERA register.
- Our page: Birla Navya. Reviews: Birla Navya, Sector 63A: Review 2026 - Price, Pros, Cons and Who It Suits and Birla Navya Sector 63a Golf Course Extension Road
Why do portals show Birla Arika possession as December 2031?
Because that is Phase 1’s date. HRERA shows Arika Phase 1 at 9 December 2031 and Phase 2 at 9 July 2033. Listings that show one date for “Birla Arika” are usually quoting Phase 1. If you are buying in Towers 4 to 6 (the Phase 2 document titles), your agreement should carry RERA-GRG-2142-2025 and the 2033 date.
Which Birla projects are nearest to possession?
By HRERA date: Navya Anaika (31 December 2026), then Navya Avik Phase 1 (30 April 2027). Both are low-rise floors in Sector 63A. Everything else is 2030 or later. Before booking a resale unit in a near-complete phase, ask for the latest quarterly progress report on HRERA and check whether an occupation certificate has been applied for.
How to verify a Birla project on HRERA
- Open the HRERA Gurugram registered projects list and search by project name (“BIRLA ARIKA”, “BIRLA PRAVAAH”, “BIRLA NAVYA”), not by “Birla Estates”: Navya sits under Avarna Projects LLP.
- Match the RERA-GRG number and the GGM registration number in your allotment letter to the row.
- Open “View” for the REP-I form: check land, unit count, carpet area and the completion date.
- Open the quarterly progress reports for construction status, and the OC/CC/PCC column for completed phases.
- Our step-by-step guide: How to Check if a Project is RERA Registered in Gurgaon (Haryana RERA Guide 2026). All registrations we track: /rera-index
Other new launches near Birla’s sectors
- Sobha Crescent Phase 1, Sector 63A: RERA-GRG-2185-2026, HRERA completion 31 March 2033. SOBHA Crescent
- Anant Raj The Estate One, Sector 63A: RERA-GRG-2197-2026, HRERA completion 21 July 2033. Anant Raj The Estate One
- For the whole corridor: Golf Course Extension Road, Gurgaon and /new-launches