In Gurugram, groundwater permission comes from the Haryana Water Resources Authority (HWRA), and you apply on hwra.org.in. Housing societies, hotels, hospitals, schools, malls and builders that draw groundwater need an HWRA NOC. The application fee for a private infrastructure project is ₹1,50,000 (₹50,000 for government bodies), and the NOC is valid for one year. Individual households are exempt only where there is no public water supply. Every assessment unit in Gurugram district (Gurugram, Gurugram Urban, Sohna, Pataudi and Farukhnagar) is classed as over-exploited in HWRA's latest categorisation, in force from 1 November 2026.

Updated 18 November 2026. We read HWRA's FAQ, its 2021 guidelines notification (fees, validity, charges and exemptions), and the block-wise groundwater categorisation as on 31 March 2025, which HWRA's Guidelines page says applies from 1 November 2026. This is the official process only, not a consultant's summary.

Who needs HWRA permission for a borewell in Gurgaon?

HWRA's FAQ says all industries, infrastructure and mining projects that use groundwater must take its permission. 'Infrastructure' explicitly includes housing societies, hospitals, schools, hotels and restaurants, malls and clubs. New buildings that need dewatering, or groundwater for construction, must get the NOC before work starts.

  • Exempt (HWRA guidelines, Appendix 5.0): individual domestic consumers in rural and urban areas, for drinking and domestic use, where public water supplies do not exist.
  • Also exempt: rural drinking-water schemes, Armed Forces and CAPF establishments, and agriculture.
  • Micro and small enterprises drawing under 10 m³ a day: no NOC, but they must register with HWRA.
  • Read the household exemption carefully. It applies only where there is no public supply. If your house has a GMDA or MCG connection, the exemption wording does not clearly cover a new borewell. Ask HWRA and your municipal body before you drill.

What is Gurugram's groundwater block category in 2026?

HWRA's 'Stage of ground water development and categorisation of the assessment units (143) as on 31.03.2025' lists all five Gurugram units as over-exploited: Farukhnagar, Pataudi, Sohna, Gurugram and Gurugram Urban. None is critical, semi-critical or safe. Statewide, the same table counts 91 over-exploited, 6 critical, 15 semi-critical and 31 safe units.

HWRA's Guidelines page says this 2025 categorisation applies from 1 November 2026. The earlier 2024 categorisation applied from 1 April 2025 to 31 October 2026. You can check a specific location with the 'Know Your Block' tool on hwra.org.in.

  • Over-exploited means NOCs for infrastructure projects are still allowed, because such projects are location-specific, but with restoration charges rather than ordinary abstraction charges (guidelines, Schedule III).
  • Construction water: in over-exploited units, groundwater may be used for construction only if no treated sewage water is available within 10 km of the site.
  • No NOC is given for groundwater for water parks, theme parks or amusement parks in over-exploited units.

How do you apply for an HWRA NOC online?

  • 1. Register and log in on hwra.org.in (the 'Login' link), then apply under your category: industry, infrastructure or mining (HWRA FAQ 4). HWRA also publishes a user manual for applying through Invest Haryana.
  • 2. Upload the documents (FAQ 11 and 13): applicant ID; land ownership proof (registry, jamabandi, allotment letter, or a utility bill under six months old); a water balance chart; a groundwater quality test report; a rainwater harvesting or recharge proposal; and a non-availability certificate from the water supplier where required.
  • 3. Infrastructure projects also add: a site plan, water demand worked out under the National Building Code 2016, the state approval letter and, for completed projects, the completion certificate.
  • 4. Projects drawing more than 500 m³ a day in an over-exploited unit (all of Gurugram) must add an impact assessment report by an accredited consultant.
  • 5. Pay the application fee online, plus 90 days' advance tariff based on your stated demand, which HWRA holds as security (FAQ 8).
  • 6. Processing takes about one month if the file is complete and there are no queries (FAQ 7).

How much are HWRA NOC fees and groundwater charges?

From HWRA Notification No. HWRA/485/Notification/2021 dated 10 September 2021:

  • Application fee, infrastructure: ₹1,50,000 for private applicants; ₹50,000 for government, PSU or semi-government bodies. Renewal is at half these rates.
  • Application fee, industry: ₹25,000 (10–100 m³/day), ₹50,000 (over 100 to 500), ₹1,00,000 (over 500 to 1,000) and ₹1,50,000 (over 1,000 m³/day).
  • Late fee: ₹1 lakh for applications filed after 15 February 2022, on top of the application fee (FAQ 3).
  • Restoration charges for infrastructure in over-exploited units (Table 5.3 B): ₹6 per m³ below 200 m³/day, ₹10 for 200 to under 1,000, ₹16 for 1,000 to under 5,000, and ₹20 at 5,000 m³/day and above.
  • Residential apartments and group housing societies using groundwater only for drinking and domestic use (Table 5.1): no charge for 0–25 m³ a month, ₹1 per m³ for 26–50 m³, and ₹2 per m³ above 50 m³.
  • Worked example (ours): a commercial project drawing 150 m³ a day in Gurugram falls in the ₹6 per m³ slab. That is ₹900 a day, or about ₹27,000 for a 30-day month, before the application fee.

How long is an HWRA NOC valid, and when must you renew?

HWRA's 2021 notification says every permission or NOC is 'valid for one year', subject to its terms. NOCs for dewatering or construction are valid for the period in the approved proposal. Renewal costs half the application fee. The '90 days' some pages call a renewal period is actually the 90-day advance tariff deposit (FAQ 8). Changing your groundwater requirement, or adding or closing a borewell after the NOC is issued, needs a fresh application and fee on the portal (FAQ 17 and 23).

What conditions come with the NOC?

  • Sewage treatment plant: compulsory for new projects needing more than 50 m³ a day of groundwater. Treated water must be used for flushing, car washing and gardening.
  • Rainwater harvesting: recharge structures designed on one-hour peak rainfall of 15–30 mm depending on area (FAQ 26), and recharge-well intake set at 75% of the borewell's average delivery (FAQ 32).
  • Dewatering projects: a digital flow meter and regular data uploads to HWRA.
  • Penalties for defaults are set out in the guidelines (FAQ 10), and HWRA has notified environment compensation for violations.

What should a flat buyer check about a society's borewell?

If a society or builder uses groundwater, ask for the HWRA NOC and check three things: the date (an NOC is valid for one year), the approved quantity, and the conditions, especially the STP and rainwater recharge. Make sure the society's water plan does not depend on an unapproved borewell. Gurugram's supply position by sector is in Gurgaon Water Supply 2026: 770 MLD Now, What Comes Next.

Add the HWRA check to your other society checks: water and sewer connections in Gurugram Water and Sewer: GMDA vs MCG and What Buyers Should Check, and fire NOC and lift registration in Fire NOC Haryana Online: Check a Gurgaon Society Before Buying.