There is no Terminal 3 under construction at Bengaluru's Kempegowda International Airport (KIA), and none is in the works planned for 2026–31. The June 2026 capital-expenditure review prepared for the airport regulator AERA covers raising Terminal 1 to about 35 million passengers a year (MPPA) and expanding Terminal 2 from 25 to 45 MPPA by 2031, taking total capacity from 51.5 to 80 MPPA. Terminal 3 is a master-plan reservation: BIAL said in 2023 that it would be built in the early 2030s, with the site fixed in the late 2020s or early 2030s depending on traffic growth.
Updated 18 November 2026. We read MECON's final report to AERA on KIA's capex for 2026–31 (June 2026), ACI Asia-Pacific's release on 2025 traffic, BookNewProperty on BIAL's environmental-clearance application (January 2026), Swarajya and India Infra Hub on the 2023 master plan, and a July 2026 report on the separate second-airport proposal.
Will there be a Terminal 3 at Bangalore airport?
Yes, in the long-term plan, but not before 2031. BIAL's master plan, which it reviews every five years, reserves space for a third terminal. In December 2023 BIAL described T3 construction as an early-2030s project, with its location to be identified in the late 2020s or early 2030s depending on traffic (Swarajya, 1 December 2023). BIAL's chief strategy and development officer said in September 2023 that the airport would have a third terminal ‘in the 2030s’ (India Infra Hub). The same 2023 plan mentioned a rail link to connect T1, T2 and eventually T3, replacing the shuttle bus.
The regulator's 2026–31 review lists 31 major packages: 9 airside, 8 terminal, 10 landside and 4 utility. None is a Terminal 3; the only ‘Terminal 3’ in the report is Delhi's, used as a comparison.
What is being built at KIA between 2026 and 2031?
- Terminal 1: upgrade from 26.5 to about 35 MPPA, with a new baggage system, screening, and MEP and ICT renewal.
- Terminal 2 Phase 2: capacity from 25 to 45 MPPA by 2031; built-up area from 255,645 sq m to 526,732 sq m (MECON found 243,855 sq m of the 271,087 sq m increase admissible).
- Aprons: a T2 Phase 2 apron with 40 stands; an 18-stand T2 Phase 2 West apron, which MECON proposed to defer. BIAL proposed raising stands from 142 to 227.
- Total passenger capacity: 51.5 MPPA now (T1 26.5 + T2 25) to 80 MPPA. Cargo capacity: 0.5 to 0.75 million tonnes a year.
How busy is Bengaluru airport now?
- Calendar 2025: 43.82 million passengers, up 8% from 40.73 million in 2024 (ACI Asia-Pacific, 12 January 2026).
- Record day: 137,317 passengers on 23 November 2025.
- Financial year 2025: about 41.8 million passengers (about 36 million domestic, 5.8 million international) and about 500,000 tonnes of cargo; third-busiest airport in India (MECON, June 2026).
- Forecast used by the regulator: 71.8 million passengers by FY2031.
- Network at 31 December 2025: 113 passenger destinations (79 domestic, 34 international).
How has the plan changed since 2023?
In December 2023 BIAL put daily traffic at about 1,05,000 passengers, with T1 handling about 70,000 and T2 about 40,000, and spoke of ‘structural capacity’ of about 92 million passengers a year by 2032–33 (Swarajya). In September 2023 it described T2 Phase 1 as built for about 25 million passengers a year, at a cost of ₹5,000 crore (India Infra Hub). By 2026 the busiest day had reached 1,37,317 passengers (23 November 2025), and the regulator's review sets out a concrete five-year path to 80 MPPA from T1 and T2 alone. What has not changed is the order of work: expand T1 and T2 first, then build T3 once traffic needs it. Articles that promise a T3 ‘by 2030’ are quoting the 2023 headline, not a 2026 decision.
When might Terminal 3 actually be needed?
This is our arithmetic, not an official forecast. The regulator's numbers give 80 MPPA of capacity against 71.8 million passengers in FY2031, which leaves about 8 million of headroom. If traffic keeps growing at 2025's 8%, it would pass 80 million in about FY2033 (71.8 → 77.5 → 83.8). That is consistent with BIAL's early-2030s T3 window. Slower growth pushes it later.
Separately, BIAL applied in January 2026 for environmental clearance to take the airport's approved capacity from 55 to 114 MPPA and cargo from 1.0 to 1.4 million tonnes a year, inside its existing campus (BookNewProperty, 11 January 2026). A clearance sets a ceiling for future building; it is not a construction start. Note that the clearance documents use 55 MPPA for today's capacity, while the AERA review uses 51.5 MPPA.
Is Terminal 3 the same as Bengaluru's second airport?
No. T3 would be a new terminal inside KIA's Devanahalli campus. The second airport is a separate greenfield proposal. In July 2026 the Minister of State for Civil Aviation told the Lok Sabha that the Airports Authority of India had completed a pre-feasibility study of three shortlisted sites, and that the Centre had not received a formal proposal from Karnataka (Deccan Herald, 28 July 2026, as republished). Our explainer: Second Airport Bangalore Location: Harohalli vs Nelamangala 2026.
What does this mean for homes near the airport?
For the next five years, the airport grows inside T1 and T2, so new jobs and traffic will build up around the existing terminals and the Devanahalli–Yelahanka corridor rather than at a new terminal site. A buyer should weigh the commute you will actually make, the Blue Line airport metro's real progress (Airport Metro Line Bangalore: 29 Stations, Oct 2026 Status), and the RERA possession date of the home. A promised third terminal is not a reason to pay more. Area guides: Kempegowda Airport and North Bangalore & the Airport Belt: 2026 Property Prices & Investment Guide. RERA-registered options in our catalogue include Godrej Reserve and Prestige Sanctuary.