To get a new BESCOM connection for a house, apply online on BESCOM's portal or at the local sub-division office, with proof of ownership or occupancy and your identity proof. The registration-cum-processing fee for a domestic lighting connection is ₹25 (₹50 for combined lighting and heating). After a site check, BESCOM issues a power sanction letter that lists the security deposits, meter deposit and the cost of any service line, which you pay before the meter is fitted. Homes up to 5 kW get single-phase supply; above that, three-phase.
Updated 19 November 2026. We read KERC's Conditions of Supply of Electricity for Karnataka (as amended to 2017, copy on BESCOM's site), KERC's Tariff Order 2025 for the temporary supply tariff, BESCOM's Citizens' Charter and online services page, and reports on the 2026 one-time window for buildings without an occupancy certificate (OC). If you bought a flat from a builder, the builder arranges the connection; see BESCOM and BWSSB Charges for a New Flat in Bangalore (2026).
Where do I apply for a new BESCOM connection?
BESCOM's ‘Apply online for LT new connection’ page sends you to one of two portals depending on location: bescom.co.in for Bengaluru and listed towns such as Anekal, Hosakote, Ramanagara and Kanakapura, and a separate portal for other areas. You can also file at the section or sub-division office. KERC's rules say the local office must help you fill the form and must acknowledge a complete application.
What documents are needed for a new connection?
- Proof of ownership (sale deed, khata or e-Khata extract, tax receipt) or proof of occupancy. If you are not the owner, the owner's consent or an indemnity bond is required.
- Proof of permanent address and PAN, if any.
- Full address, location sketch, phone number and the name of a nominee.
- Sanctioned building plan for larger buildings (Clause 9; see below).
- Licensed electrical contractor's completion-cum-test report and wiring diagram after wiring is done. You need not name the contractor in the form for a domestic load below 7.5 kW.
- An undertaking that a solar water heater is installed, for homes of 600 sq ft or more on sites of 1,200 sq ft or more in municipal and BDA areas (see Is a Solar Water Heater Mandatory in Bangalore? Rules, Rebate).
How much does a BESCOM new connection cost?
KERC's Conditions of Supply fix only the small fees. The rest depends on your load and whether a new line or transformer is needed, and it is set out in your power sanction letter.
- Registration-cum-processing fee: ₹25 domestic lighting; ₹50 combined lighting and heating; minimum ₹250 per premises for Clause 9 buildings.
- Initial security deposit: an advance against your bills, at the rate KERC sets; refundable with interest when the contract ends.
- Meter security deposit: per BESCOM's schedule of rates.
- Service line or network cost: under KERC's Recovery of Expenditure Regulations 2004, only if a line or plant has to be built.
- Tatkal: pay ₹1,000 extra per installation to get supply within 8 days of filing complete documents, for loads up to 5 kW where an LT line already exists.
How does a temporary connection for construction work?
While you build, you take a temporary supply. Under Clause 12 of the Conditions of Supply, there is no registration fee; you pay a service charge of ₹50 per LT installation and an advance on estimated consumption, worked out at 12 units per kW per day for the period. The advance is adjusted against actual bills, and any balance is refunded on request or moved to your permanent account. Loads under 50 kW take LT supply.
Temporary supply is billed under tariff LT-7 through a prepaid meter. For 2026-27, KERC's rate is ₹200 per kW per month plus 1050 paise (₹10.50) per unit, nearly double the ₹5.80 domestic rate. If you demolish and rebuild, the old connection must be surrendered and a fresh one taken; the old meter cannot be used for construction.
To move from temporary to permanent: finish wiring, get the licensed contractor's completion-cum-test report, apply for the permanent connection with your documents, pay the sanctioned deposits, and ask for the temporary connection to be disconnected and the advance balance adjusted.
Can I get a BESCOM connection without an occupancy certificate?
Since 2025, utility connections for new buildings in Bengaluru have been tied to building approvals, which held up many owners without an OC or completion certificate. Two separate relaxations followed. First, the Greater Bengaluru Authority exempted small homes from needing an OC: a September 2025 notification for plots up to 1,200 sq ft (ground + 2 or stilt + 3), extended by a government order of 5 June 2026 to plots up to 2,400 sq ft with 20% tolerance and up to ground + 3 floors. Plan approval and safety norms still apply.
Second, a government order of 22 June 2026 gave a one-time 15-day window for power connections to existing G+3 or S+4 residential buildings of up to 2,400 sq ft (with up to 20% deviation) completed on or before 31 May 2026, including in municipal and panchayat areas. Applications went to the ESCOM sub-division office with geo-tagged photos. That window has closed. For a new house today, build to an approved plan and keep the OC or exemption papers ready. More detail: OC Exemption in Bangalore 2026: Buying a House Without an OC and Nambike Nakshe 2.0: 30-Minute Building Plan Approval (2026).
What load should I ask for, and when do I need three-phase?
- Single phase, 230 V: all non-motive loads up to and including 5 kW.
- Three phase: above 5 kW. Homes with several air conditioners, an induction hob and an EV charger usually cross 5 kW.
- Clause 9 applies if the building needs 35 kW or more, or has a built-up area above 800 sq m: you must submit the sanctioned plan, ownership proof, any BESCOM NOC for plan sanction and a route sketch, and the minimum fee is ₹250 per premises.
- Sanctioned load drives your fixed charge (₹150 per kW per month in 2026-27; see /blog/bescom-tariff-2026-27-per-unit-bangalore-homes), so do not over-ask.
How long does it take, and how do I track it?
BESCOM's Citizens' Charter commits to a feasibility report and power sanction within about 7 working days for domestic lighting, 2 working days for temporary supply, and 15 working days for Clause 9 buildings. After you sign the agreement and pay deposits, a domestic connection is to be serviced within 30 days. Temporary supply up to 5 kW is to be given within 3 days. Track the application on the portal you used, quoting your application number, or at the sub-division office.
Why are new connection applications rejected or held?
- Ownership or occupancy proof missing, or in a different name, with no owner consent or indemnity bond.
- No contractor's completion-cum-test report or wiring diagram.
- No solar water heater undertaking where it applies.
- Building plan or OC issues for buildings outside the exemptions.
- Load above 5 kW asked for on single phase, or Clause 9 papers missing for a larger building.
- Using an old meter for construction after demolition.