The Karnataka stretch of the Bangalore–Chennai Expressway (NE-7) is fully open. All 71 km, from Hoskote to Bethamangala near KGF, has carried traffic since 9 December 2024. It was built as three packages of 26.4 km, 27.1 km and 17.5 km. Since June 2026 a further 25 km in Andhra Pradesh, from Bethamangala to Baireddipalle, is also open, so you can now drive about 100 km from Hoskote without a break. NHAI officials have given December 2026 as the target for the full road to Chennai.
Updated 17 November 2026. We checked the Karnataka package table (chainage, length and contractor), the June 2026 report on the Andhra extension and the Baireddipalle toll revision, the September 2025 report on toll collection in Karnataka, the October 2026 status of the STRR Hoskote–Hosur link and the KR Puram–Hoskote metro plan, and we worked out road distances from east Bengaluru to Hoskote.
Which packages make up the 71 km Karnataka stretch?
Phase 1 of the expressway is the Karnataka section. The package table published by The Metro Rail Guy gives exact chainages, and they add up to 71.0 km:
- Package 1, Bangalore (Hoskote end) to Malur: Km 0.000 to Km 26.400, 26.40 km, Dilip Buildcon
- Package 2, Malur to Bangarpet: Km 26.400 to Km 53.500, 27.10 km, Dilip Buildcon
- Package 3, Bangarpet to Bethamangala: Km 53.500 to Km 71.000, 17.50 km, KCC Buildcon
- Status: all three packages opened to traffic on 9 December 2024; Wikipedia notes the formal inauguration was still pending when last edited
Where do you join the expressway near Bangalore?
The Bangalore end is at Hoskote. When toll collection began in September 2025, Oneindia named Hedigenabele, near Hoskote, as the Hoskote-end plaza and Sundarapalya, near KGF, as the plaza at the other end of the Karnataka stretch. The same report also listed plazas at Agrahara and Krishnarajapura but did not say where they are.
We could not open an official NHAI list of interchanges. The two towns between Hoskote and the state border are Malur and Bangarpet, where the package boundaries fall. Before you rely on a particular ramp, check the signs on the road. The Hans India report of 29 June 2026 adds a useful rule: vehicles that use only the entry or exit ramps do not pay toll at the Baireddipalle plaza. Only vehicles on the main carriageway pay.
Drivers heading for Chittoor, Tirupati or Chennai can use the open section for much of the trip, then switch to district roads and national highways after leaving it.
What toll do you pay on the Karnataka stretch?
NHAI started collecting toll on the 71 km Hoskote–KGF stretch on 4 September 2025. These are the rates reported then (Oneindia, 6 September 2025):
- Car, Hedigenabele to Sundarapalya: ₹185 one way, ₹275 round trip
- Car, Sundarapalya to Hedigenabele: ₹190 one way, ₹280 round trip
- Car monthly pass: ₹6,105 for 50 one-way trips, or ₹6,260 for round trips (as reported)
- Light goods vehicles, minibuses, buses and trucks: ₹295 to ₹955, depending on class and number of trips
- Design speed: 120 km/h
Toll rates are revised each year. Revised rates came into force at the Baireddipalle plaza in Andhra Pradesh on 25 June 2026, but the report did not give the new figures. We could not open a 2026–27 rate notice for the Karnataka plazas, so treat the figures above as the September 2025 launch rates and check your FASTag statement for the current charge.
When will the full road to Chennai open?
On 29 June 2026, The Hans India quoted NHAI officials who expected the full 262 km expressway, including the Tamil Nadu section, to be running by December 2026. At that point about 11 km was left between Baireddipalle and Bangarupalem in Andhra Pradesh, including wildlife underpasses, and work there was waiting for forest clearance. Bangarupalem to Gudipala was complete, and two of the three Andhra packages were finished.
Not every source gives the same date or length. Wikipedia, last edited in November 2026, lists 2027 for full completion and 258 km for the length. NHAI officials' figure is 262 km. We give the NHAI figure, and we treat December 2026 as a target, not a confirmed opening date. For a fuller history of the opening dates, see Bangalore Chennai Expressway Opening Date: Hoskote Side.
How far is Hoskote from east Bangalore?
For buyers, what matters is how quickly you can reach the Hoskote end from where you work. These are road distances to Hoskote town centre (Channabyregowda Circle). Times are free-flow estimates with no traffic, so expect longer at peak hours:
- Whitefield (Kadugodi station): 10.6 km, about 11 min
- Budigere: 13.8 km, about 14 min
- Varthur: 16.7 km, about 17 min
- KR Puram (railway station): 17.4 km, about 15 min
- Indiranagar: 20.1 km, about 17 min
- Marathahalli: 20.5 km, about 20 min
- MG Road: 23.0 km, about 21 min
- Hebbal: 26.2 km, about 29 min
- Sarjapur town: 27.5 km, about 28 min
- Electronic City: 36.9 km, about 39 min
What else is changing around Hoskote?
- STRR Hoskote–Hosur (21 km): NHAI is looking at opening finished sections in phases from as early as December 2026. The girder over the Bengaluru–Chennai railway line at Lingadeeramallasandra is targeted for December 2026, and the second carriageway's girder for March 2027 (Oneindia, 23 October 2026). See STRR Hoskote–Hosur Stretch: Opening by December 2026?.
- STRR Dobbaspet–Hoskote (80 km): open since 11 March 2024. It links Hoskote to Doddaballapur and the airport side.
- KR Puram–Hoskote metro: a 16.3 km line with 11 stations (KR Puram, ITI Bhavan, TC Palya, Bhattarahalli, Bhattarahalli Junction, Medahalli Junction, Avalahalli, Budigere Cross, Katamnallur Gate, Hoskote Toll Plaza and Hoskote Government Hospital). BMRCL is preparing the detailed project report, and no construction or opening dates have been set (Construction World, 8 October 2026). See KR Puram to Hoskote Metro Plan (Nov 2026): 11 Stops, Status.
- Cauvery Stage 6: approved by the state on 26 February 2026 at about ₹7,000 crore. Hoskote is one of the eight local bodies it will supply. Funding was still being sought from lenders, and no completion date was given (Oneindia, 27 February 2026).
What does it mean if you are buying near Hoskote or Old Madras Road?
The expressway mainly helps trips east, towards Kolar, KGF, Chittoor and, later, Chennai. Daily commutes into the city still run on Old Madras Road (NH-75) or the STRR. If you will use the expressway often, add the toll to your monthly budget. At the September 2025 rates, a car monthly pass costs ₹6,105.
Before you choose a home, check how far it is by road to the Hoskote end, not just in a straight line. Visit at peak hour. Check the project's Karnataka RERA registration and completion date. For area context, see Hoskote, Bangalore, Old Madras Road, Bangalore and Hoskote. Projects in our catalogue near this end include Sobha Galera and Brigade Buena Vista. For a wider view of the area, read Hoskote, Bengaluru: Buyer's Guide 2026 — Prices, Metro, Projects and Risks.