UER-2 (Urban Extension Road-II, NH-344M) collects its toll at the Mundka–Bakkarwala plaza near the Mundka Industrial Area metro station. Since May 2026 that plaza has been barrier-free, so FASTag and number-plate cameras charge you without a stop. Residents within 20 km had a ₹350 monthly pass for 2025-26, according to NHAI's submission in the Delhi High Court. The national FASTag annual pass costs ₹3,075 for 2026-27. NHAI's own fee portal could not be opened on 18 November 2026, so check the current per-trip car fare in the Rajmargyatra app before relying on any figure, including the ₹235 quoted in court reports.

Updated 18 November 2026. We read PIB's release on the August 2025 inauguration, NHAI's toll and pass rules as reported by ANI, PTI and News On AIR, the May 2026 barrier-free launch report and the UER-II project summary. This guide explains UER-II for Gurgaon buyers on the Dwarka Expressway, whose own toll is covered in Dwarka Expressway Toll Pass 2026: Annual Pass, Rules.

Is Dwarka Expressway the same as UER-2?

No. They are two different national highways that meet at the Delhi–Haryana border near Dwarka. The Dwarka Expressway runs from Shiv Murti on NH-48 through Dwarka to Kherki Daula in Gurugram. UER-II is a ring road around outer Delhi, running from Alipur on NH-44 in the north, through Bawana, Rohini, Mundka and Najafgarh, to Dwarka in the south-west.

  • Dwarka Expressway, Delhi section: 10.1 km at about ₹5,360 crore. Package I is 5.9 km from Shiv Murti to the RUB at Dwarka Sector 21. Package II is 4.2 km from that RUB to the Delhi–Haryana border, 'providing direct connectivity to UER-II' (PIB, 16 August 2025).
  • Dwarka Expressway, Haryana section: 19 km, opened in March 2024 (PIB).
  • UER-II: the Alipur–Dichaon Kalan stretch with new links to Bahadurgarh and Sonipat, built for about ₹5,580 crore. Both projects were inaugurated on 17 August 2025 at Rohini (PIB).
  • Overlap: The Metro Rail Guy's project page notes that about 7.5 km of UER-II was built as part of Dwarka Expressway packages 1 and 2, which is why maps make them look like one road.

What is the UER-2 route?

The Metro Rail Guy's project summary (last updated around 14 August 2025) gives the scheme as 74.98 km in all. Part of its status section is out of date, because it still lists a December 2024 deadline.

  • Main road (Phase 1): 38.111 km, six lanes, from NH-1 (now NH-44) at km 23.8 near Bankoli village to near Dwarka Sector 24.
  • Bahadurgarh spur: 7.269 km, four lanes.
  • Sonipat spur: 29.6 km, four lanes.
  • Right of way: 100 m. Cost: ₹7,715.60 crore, including ₹4,000 crore of viability gap funding from DDA.
  • Purpose, per PIB: to ease traffic on the Inner and Outer Ring Roads and at Mukarba Chowk, Dhaula Kuan and NH-09, and to give direct access to Bahadurgarh and Sonipat.
  • Future phases (IGI–Vasant Kunj–Tughlakabad and beyond) are at DPR or construction stage, according to Wikipedia's summary. We found no official completion dates for them.

How much is the UER-2 toll and where is the plaza?

The plaza is at Mundka–Bakkarwala, near the Mundka Industrial Area metro station (ANI, 26 September 2025). Here is what official and court-reported sources say:

  • Per-trip fare: the only figure in court reporting is ₹235 a crossing. That was the petitioner's own claim in a Delhi High Court case, not an NHAI tariff, and press figures for this plaza vary. Check the live car fare in the Rajmargyatra app or on tis.nhai.gov.in.
  • Monthly pass: ₹350 for 2025-26 for non-commercial vehicles of residents within 20 km. NHAI's counsel cited a gazette notification of 20 August 2025 and Rule 9(3) of the National Highways Fee Rules, 2008. Justice Sachin Datta dismissed the challenge to the plaza (ANI, 26 September 2025). The amount is revised every year.
  • Barrier-free tolling: Nitin Gadkari launched multi-lane free-flow (MLFF) tolling at this plaza in May 2026, India's second after Choryasi on NH-48 in Gujarat (The Pioneer, 12 May 2026). FASTag and automatic number-plate recognition (ANPR) charge you on the move.
  • Low balance: if your FASTag is short of funds or invalid, you get an e-notice and have 72 hours to pay online (The Pioneer).

Does the FASTag annual pass work on UER-2?

UER-II is a National Highway (NH-344M), and the Delhi High Court case shows NHAI defending the plaza. The national FASTag annual pass is valid at fee plazas on National Highways and National Expressways. For 2026-27 it costs ₹3,075 for one year or 200 crossings, whichever ends first, for non-commercial vehicles with a valid FASTag (News On AIR, 15 March 2026). Confirm in the Rajmargyatra app that the pass shows as valid for Mundka–Bakkarwala before you rely on it.

Separately, from 1 November 2026 MoRTH created an annual local pass for residents within 20 km of a plaza: ₹1,500 a year at plazas outside municipal limits and ₹3,000 inside them. It is valid only at the plaza it is issued for, and the existing monthly pass is ₹360 (PTI via ThePrint, 27 October 2026). The rules exclude roads where a service road or alternative road exists. Our sources do not say whether Mundka–Bakkarwala qualifies, so ask at the plaza or in the app.

How do Gurgaon residents reach UER-2?

From the Dwarka Expressway sectors (roughly Sectors 99 to 113), drive north on the Expressway past the Bijwasan plaza to the Delhi–Haryana border. Package II continues into Dwarka and connects directly to UER-II (PIB). From there UER-II runs north through Najafgarh and Mundka towards Bahadurgarh, Rohini, Bawana, Sonipat and Alipur on NH-44.

A trip from Gurgaon to the northern end can therefore cross two NHAI plazas: Bijwasan on the Dwarka Expressway (about ₹220 one way and ₹330 return for a car, as reported by Outlook Money in November 2025) and Mundka–Bakkarwala on UER-II. That is why the national annual pass can suit frequent drivers. We found no official travel-time figures from Gurgaon sectors to Rohini, Mundka or NH-44, so we do not quote any. For the airport side, see Gurgaon to IGI Airport by Sector: Road km and Time (2026).

What does UER-2 mean for Dwarka Expressway home buyers?

UER-II mainly helps drivers heading north and west: Bahadurgarh and the Rohtak road, Sonipat, Rohini and NH-44 towards Panipat and Chandigarh. Before UER-II, those trips meant crossing central Delhi. It does not change trips to Cyber City or Golf Course Road. Count the extra tolls in your running costs if you will use it daily, and check whether you qualify for a local pass.

For the corridor itself, see Dwarka Expressway, Gurgaon, the road's status in Is Dwarka Expressway Completed? 2026 Status, Cost per Km, NHAI and the sector map in Dwarka Expressway 2026: A Sector-by-Sector Buyer's Map.