In the local planning areas under BMRDA (Hoskote, Anekal, Nelamangala, Magadi, Kanakapura, Doddaballapura, BIAAPA and others), BMRDA’s service sheet lists these charges for a residential layout. Scrutiny fee: ₹1,000 per acre. Web charges: ₹2,000 up to 2 acres, or ₹5,000 above. Betterment levy: 0.5% of the market value per sq m, with a minimum of ₹25 per sq m. Lake rejuvenation fee: ₹25 per sq m. Cess and surcharge: 1.0% of market value in total. On our worked example, a 5-acre layout at an assumed ₹10,000 per sq m market value pays about ₹35.5 lakh, roughly ₹16 per sq ft of land.
Updated 17 November 2026. We read BMRDA’s published service procedure for draft layout approval and release of sites under Section 17 of the Karnataka Town and Country Planning Act, 1961, and checked it against BMRDA’s list of 12 local planning authorities.
What fees does a layout pay at the draft approval stage?
- Scrutiny fee: ₹1,000 per acre of land.
- Web charges: ₹2,000 up to 2 acres; ₹5,000 for more than 2 acres.
- Betterment levy (paid before approval; Notification UDD.3.TTP2015 dated 25 February 2020), as a percentage of market value per sq m of non-agricultural land:
- Residential: 0.5%, minimum ₹25 per sq m.
- Industrial: 1%, minimum ₹37.5 per sq m.
- Commercial: 1.5%, minimum ₹62.5 per sq m.
- Others: 0.5%, minimum ₹25 per sq m.
- Additional fee under Section 18(1-A) for rejuvenating lakes or tanks: ₹25 per sq m of land or plot, for all local planning areas in the region.
- Cess and surcharge under Section 37-C, as a percentage of market value per sq m: water supply cess 0.2%, ring road surcharge 0.2%, slum improvement cess 0.1% and mass rapid transport surcharge 0.5%, a total of 1.0%.
How much would a 5-acre layout pay? A worked example
The market value below is our assumption for illustration only. Use the guidance value for your survey number (see Bangalore guidance values) and ask the authority which value and area it applies.
- Land: 5 acres = 20,234 sq m (1 acre = 4,046.86 sq m).
- Assumed market value: ₹10,000 per sq m.
- Scrutiny fee: 5 × ₹1,000 = ₹5,000.
- Web charges: ₹5,000 (above 2 acres).
- Betterment levy: 0.5% × ₹10,000 = ₹50 per sq m (above the ₹25 minimum) × 20,234 = ₹10.12 lakh.
- Lake fee: ₹25 × 20,234 = ₹5.06 lakh.
- Cess and surcharge: 1.0% × ₹10,000 = ₹100 per sq m × 20,234 = ₹20.23 lakh.
- Total: about ₹35.51 lakh, or about ₹175 per sq m (about ₹16 per sq ft) of gross land.
What are the stages and time limits?
- Draft layout approval, Section 17(1), (2) and (2-A): apply with title deeds, RTC, conversion orders, EC in Forms 15 and 16, mutation, water NOC, ADLR survey sketch, village map, total-station survey and a zoning-compliant plan. KSPCB consent for establishment is needed above 10 acres. Time limit: 90 days under Sakala.
- Release of sites or final layout, Section 17(2-B): apply with completion NOCs for roads (urban local body, or the Panchayat Raj Engineering Department outside urban limits), water and drainage (KUWS&DB or rural water supply), electrical works (BESCOM), parks (Horticulture Department), KSPCB consent to operate the STP above 10 acres, and photographs. Time limit: 60 days.
- Appeals: first to the authority’s commissioner within 15 days, then to the Metropolitan Commissioner, BMRDA.
- Who can apply: the landowner, or a GPA holder (with a JDA if applicable).
Has land conversion changed for layouts?
Yes, according to legal commentary. The Karnataka Land Revenue (Amendment) Rules, 2025 (Notification RD-LGP/6/2025, 17 September 2025), as summarised by Cyril Amarchand Mangaldas, let the planning authority verify, collect fees and issue digitally signed conversion certificates for land that matches an approved master-plan zone. Outside master-plan areas, the Deputy Commissioner decides. An application not acted on within 30 days is treated as approved.
Why should a plot buyer care about these charges?
- Paid charges and a release order are what separate an approved layout from a ‘revenue’ or unapproved one. Ask for the payment receipts along with the orders.
- The release stage needs proof of roads, water, power and parks, so a released layout has had its basic works certified.
- In gram panchayat areas, 2025 RDPR rules reported by The Realty Today require roads, parks and civic amenity areas to be handed over by a registered relinquishment deed, and no new PID or khata until a planning authority has approved the layout plan.
- Penalties for unauthorised development are a separate topic. See Layout Penalty Karnataka 2026: 3% a Year for 2005-15 Layouts.
- Area-by-area approval checks: BMRDA Approved Plots in Bangalore 2026: Project List and BDA vs BMRDA vs BIAAPA Approved Layouts: Which Authority Governs Your Plot?.