A Section 6 extension moves the completion date in a project’s RERA registration, not the possession date in your agreement. Under Section 6 of the RERA Act, HRERA can extend a registration for force majeure, or in ‘reasonable circumstances’ without the promoter’s default, for up to one year in total. On 11 August 2026, HRERA Gurugram extended every registered project whose completion date falls on or after 28 February 2026 by four months, with no application needed. For delay interest, HRERA works from the due date in your agreement for sale.
Updated 17 November 2026. We read HRERA Gurugram’s order No. 9/1-2026 dated 11 August 2026, Section 6 and Rule 6, the HRERA Gurugram standard-fee regulations (2021, substituted text gazetted 20 August 2026), and two HRERA Gurugram orders that computed due dates in projects with extended registrations. No project is named.
What did HRERA Gurugram’s August 2026 extension order say?
- Order No. 9/1-2026 HARERA/GGM (Admn), dated 11 August 2026, issued under Sections 6, 7(3), 34(f) and 37 of the RERA Act.
- Who gets it: every project registered with HRERA Gurugram whose completion date, revised completion date or extended completion date falls on or after 28 February 2026.
- How much: completion timelines ‘shall stand extended automatically by a period of four (04) months’.
- Why: the situation in West Asia, which the order says has hit supply chains and caused shortages of construction materials, and which the Department of Expenditure has treated as ‘war’ for force majeure purposes.
- No separate application is needed.
- Limit: only projects registered, and extensions or continuations granted, on or before 31 July 2026.
- Basis: issued under Section 83 following the Ministry of Housing and Urban Affairs advisory No. O-17024/66/2018-HOUSING-UD/E-9042100 dated 31 July 2026.
- The order says nothing about buyers’ agreements for sale.
How does a promoter apply for a Section 6 extension?
- Form REP-V under Rule 6, filed three months before the registration expires.
- Fee: half the registration fee, plus an explanatory note on the reasons for delay and why the extension is needed, with supporting documents.
- The Authority may waive the extension fee where the delay is due to force majeure, court orders or government policy.
- Section 6 says an application cannot be rejected without a hearing. Under Rule 6 the promoter may get 30 days to fix defects in the application.
- Outcome: Form REP-VI if granted, Form REP-IV if rejected.
- Force majeure in Section 6 means war, flood, drought, fire, cyclone, earthquake or any other natural calamity affecting development. The ‘reasonable circumstances’ route needs no default by the promoter and written reasons, and all extensions together cannot exceed one year.
- After that one-year cap, HRERA can let a registration ‘remain in force’ under Section 7(3) on conditions. The fee schedule treats that separately.
What does a RERA extension cost in Gurugram? A worked example
Registration fee (Schedule I): ₹10 per sq m for residential in hyper or high-potential zones and ₹5 in medium or low-potential zones; ₹20 and ₹10 for commercial; ₹10 for plotted colonies. Group housing rates are ‘up to 100 FAR’ and ‘proportionately higher for higher FAR’. The extension fee is half the registration fee. HRERA Gurugram’s standard-fee regulations add a processing fee of ₹10 per sq m of total floor area as per FAR, and a late fee of 50% of the extension fee for the first month’s delay plus 50% for each further month or part. These replaced the 2019 late-fee regulation at the same rates.
- Illustration: a 10,000 sq m group-housing site in a high-potential zone with FAR of 175%.
- Registration fee: 10,000 × ₹10 × 1.75 = ₹1,75,000.
- Extension fee (half): ₹87,500.
- Processing fee: 17,500 sq m floor area × ₹10 = ₹1,75,000.
- If filed two months late: 50% + 50% of ₹87,500 = ₹87,500 extra.
- Continuation under Section 7(3): half the registration fee for each year sought, plus ₹10 per sq m processing.
Does a registration extension change my possession date or delay interest?
Not automatically. Section 18(1)(a) ties delay interest to the promoter failing to give possession ‘in accordance with the terms of the agreement for sale’ or ‘by the date specified therein’. HRERA Gurugram works from that agreement date. In Complaint No. 5252 of 2024 (decided 23 July 2025), the project’s registration had been extended under Section 6 and continued under Section 7(3). HRERA still took the due date from the agreement clause and refused the promoter’s request for a six-month COVID-19 grace period, because the agreement was signed after COVID.
Where an agreement was signed before COVID-19, HRERA has added the six-month COVID grace (from its 26 May 2020 notification) when computing the due date. Complaint No. 764 of 2024 is an example. So force majeure periods can count, case by case. Whether the 2026 four-month extension will be added to individual due dates is for the Authority to decide in each case. The August 2026 order does not say.
The extension date does matter in one place. Under clauses 1.2(ii) and 1.3 of the Haryana model agreement, a tax or development-charge increase that comes after the registered completion date ‘which shall include the extension of registration’ cannot be charged to you.
How do I check whether my project’s registration was extended?
- Open the project on HRERA’s ‘Search Projects’ page and read the registration certificate and any extension (REP-VI) or continuation entries. For a walk-through, see How to Read a RERA Project Page, Step by Step: K-RERA, HRERA Gurugram and TNRERA.
- HRERA Gurugram also publishes ‘Registered Projects’, ‘Lapsed Projects’ and ‘Defaulter/Cancelled/Suspended/Abeyance Projects’ lists, and public notices.
- Compare three dates: your agreement’s possession date, the registered completion date, and any extended date. Use the first for delay interest and the second for the tax and charges clause.
- Newly registered projects, with their registered completion dates, are listed at New Hrera Registrations, Gurgaon. Check the licence too: How to Verify a DTCP Licence and HRERA Registration in Gurgaon, Step by Step. For delay claims, see HRERA Delay Interest Gurugram 2026: Rate & How to Calculate and GRAP Construction Ban Gurgaon 2026: Possession Dates.