Updated 5 November 2026. We read the RERA Act on the HRERA website, the K-RERA quarterly-update circular as reported, ANAROCK's Bengaluru Q2 2026 report, the Knight Frank H1 2026 report and ANAROCK's Q3 sales as reported. The July–September 2026 updates were due by 15 October 2026, so they should now be on project pages.

What K-RERA booking data is

  • The legal duty: Section 11(1) requires the promoter to keep the project web page updated quarterly with the list of apartments or plots booked, by number and type (clause b), and the garages booked (clause c).
  • When: within 15 days of each quarter's end, so by 15 July, 15 October, 15 January and 15 April (K-RERA circular of 19 June 2026, as reported by TeamLease RegTech).
  • Who reports it: the promoter. The booked count is a self-declared figure; the regulator publishes it but does not audit each booking.
  • Scale: Karnataka RERA's public register listed 4,793 project rows for Bengaluru Urban and Bengaluru Rural districts when we last read it on 28 October 2026 (Property Point's RERA dataset). Phases and towers are often registered separately.

How to work out a project's booked share: 6 steps

  • 1. Find the project on rera.karnataka.gov.in by its registration number (walkthrough: How to Check RERA Registration in Karnataka: 7 Steps).
  • 2. Note total units registered for that registration number, by type. A large project can have several registration numbers; treat each one separately.
  • 3. Open the latest quarterly update and note units booked. Check the quarter it covers: after 15 October 2026 it should be July–September 2026.
  • 4. Booked share = units booked ÷ units registered. Example (illustrative): 312 booked of 480 registered is 65%.
  • 5. Read the last four updates in a row. A falling booked count can mean cancellations; a flat count over several quarters means slow sales or late filing.
  • 6. Compare with the launch date. A project registered two quarters ago at 30% booked is in a different position from one registered three years ago at 30%.

How to build a locality figure

Pick projects in one area registered in the same window, say January 2025 to June 2026. Add their registered units and their booked units, then divide. Report the share with the number of projects and the quarter of the data, for example '11 projects, 5,840 units, 52% booked as of September 2026' (illustrative numbers). Leave out any project whose latest update is more than one quarter old, and say how many you left out.

A common question among buyers is whether a citywide figure built this way, such as 'about a third of units launched since 2025 are booked', is reliable. It can be a useful indicator, but its accuracy depends entirely on how many projects filed on time and how booking is defined in each filing. We have not seen an official K-RERA aggregate of this kind.

What the booking count does not tell you

  • Booked is not registered: a booking may be backed by a token or a booking amount; an agreement for sale and a loan may come later.
  • Cancellations: a unit can be booked, cancelled and re-booked between filings.
  • Released vs registered: developers often release a few towers first, so a 'sold out' launch can still show a low booked share of registered units.
  • Late or missing filings: in September 2025 the Karnataka High Court set aside K-RERA's 2020 circular levying a delay fee on late quarterly updates (LiveLaw, 23 September 2025); K-RERA's 2026 circulars restate the duty. Check the date of the last update before relying on it.
  • Price: the update does not say at what price units were booked or whether discounts applied.

Bengaluru's unsold stock: the two counts

  • ANAROCK, end of Q2 2026: about 79,200 homes available, up 34% in a year and 9% in a quarter; overhang about 15 months; East Bengaluru held 49% and North 28%. Its definition counts launched but unsold units whatever their construction stage.
  • Knight Frank, end of H1 2026: 74,299 unsold homes, up 22% in a year; 5.3 quarters to sell at the trailing pace; average age of unsold stock 14.4 quarters. ₹50 lakh–1 crore homes were 30% of unsold stock and ₹1–2 crore 28%.
  • Sales pace: ANAROCK counted about 15,300 sales in Q2 2026 and about 16,670 in Q3 2026, up 12% year on year (Construction World, 30 September 2026). Knight Frank counted 27,968 sales in H1 2026, up 5%.
  • Our reading: both say stock rose faster than sales over the year. Their totals differ because each tracks its own set of projects.