As the RERA Act completes 10 years, 3,147 of the 8,984 projects approved for registration with Karnataka RERA (K-RERA) have lapsed, and only 3,580, or 39%, have applied for completion. The figures were compiled by the homebuyers' group Forum for People's Collective Efforts (FPCE) and reported by The Hindu on 4 November 2026.
Updated 5 November 2026. We also read K-RERA's own homepage counters and counted every project row in the Bengaluru Urban and Bengaluru Rural registers on the K-RERA portal. This page gives aggregate numbers only; it does not name any project.
Karnataka RERA at 10 years: the key numbers
- Projects approved for registration, statewide: 8,984 (FPCE data, The Hindu, 4 Nov 2026).
- Lapsed: 3,147, or about 35% of approved projects (FPCE data, The Hindu).
- Applied for completion: 3,580, or 39% (FPCE data, The Hindu).
- Not covered by either figure: about 2,257 projects, our subtraction (8,984 − 3,147 − 3,580). The report does not say how these split, and the subtraction assumes no project is counted in both groups.
- Projects that have applied for registration: 10,630 (K-RERA homepage counter, read 5 Nov 2026).
- Complaints registered with K-RERA: 13,889 (K-RERA homepage counter, 5 Nov 2026).
- Project extensions approved: 989 (K-RERA homepage counter, 5 Nov 2026).
- Real estate agents who have applied for registration: 8,711 (K-RERA homepage counter, 5 Nov 2026).
What do 'lapsed' and 'applied for completion' mean?
When a promoter registers a project, it declares a completion date, and the registration runs to that date. Section 6 of the RERA Act lets the authority extend a registration if the delay is due to force majeure, or in reasonable circumstances without default by the promoter, for a total of up to one year. A project whose registration period has ended, without completion being filed or an extension in force, is commonly described as lapsed.
Applying for completion means the promoter has told the regulator the project is finished, usually backed by the planning authority's completion or occupancy papers. The Hindu's report reads the 39% figure as a sign that many projects in the state have not reached completion within their stated timelines. A lapsed status does not by itself tell you whether construction has stopped, slowed or finished without the paperwork being filed; the project page on the portal is where to check.
Bengaluru's share: what the K-RERA register shows
We read every row of the Bengaluru Urban and Bengaluru Rural project registers on the K-RERA portal on 5 November 2026: 5,182 entries in all. The register's status column shows approval, rejection, withdrawal, transfer or revocation; it does not mark projects as lapsed or completed, so this split is not comparable with FPCE's statewide figures.
- Approved: 4,763 entries, of which 34 are transfer-of-registration records, leaving 4,729 project registrations (4,064 in Bengaluru Urban, 665 in Bengaluru Rural).
- Rejected: 306. Withdrawn: 72. Transferred: 35. Revoked: 6.
- By type, of the 4,729: 3,346 residential or group housing, 1,185 plotted developments, 119 mixed developments and 79 commercial.
- Completion date moved: 1,530 of the 4,729 (32%) now show a later proposed completion date than the one declared at registration, our count. The register's columns show this includes the COVID-19 extension and Section 6 extensions.
- Completion date passed: 3,225 of the 4,729 (68%) have a latest proposed completion date before 5 November 2026, our count. The register list does not show how many of these have finished or applied for completion.
How many projects does Bengaluru register each year?
Approvals in Bengaluru Urban and Bengaluru Rural by year of approval, from the same register (our count; 2017 includes ongoing projects that had to register when the law came in; 2026 is to 5 November):
- 2017: 799
- 2018: 692
- 2019: 424
- 2020: 306
- 2021: 287
- 2022: 441
- 2023: 451
- 2024: 439
- 2025: 520
- 2026 (to 5 Nov): 370, including 50 in October, the highest monthly count since January 2025. The October list is at New RERA Projects in Bangalore: October 2026 List
What this means if you are buying
The statewide numbers say that a declared completion date is a promoter's estimate, not a promise the market has always kept. That makes three checks worth doing on any project, new or old:
- Open the project on the K-RERA portal and compare the 'proposed completion date at the time of registration' with the current one. A later date means an extension. Our step-by-step guide: How to Check RERA Registration in Karnataka: 7 Steps
- Read the quarterly progress reports for bookings and construction stage: K-RERA Quarterly Progress Report: Check Construction, Oct 2026
- Check the annual audit report filing, due 15 November 2026 for 2025-26: K-RERA Form-7 Audit Due 15 Nov 2026: What Buyers Can Check
- Ask for the occupancy and completion papers before possession: Occupancy Certificate vs Completion Certificate in Bengaluru: What to Demand Before You Take Possession
- If your project's date has passed, the 2026 four-month extension may apply: K-RERA 4-Month Extension 2026: What It Means for Possession. For complaints: How to File a Complaint in Karnataka RERA: 2026 Guide
What K-RERA has issued recently
On 5 November 2026 the K-RERA homepage listed, among its latest notices, a circular on penalties for late or missing quarterly updates for 2026-27, a notice on the procedure for recovering monetary and non-monetary reliefs ordered on complaints under Section 31, and a notice on extending project registrations on force majeure grounds under the Union housing ministry's advisory. The recovery procedure is explained in K-RERA Order Not Paid? Execution Petition and Recovery, 2026.