A Gurgaon builder can ask for advance maintenance only when it makes a valid offer of possession (after the occupation certificate), and for no more than one year, even if the agreement says more. HRERA Gurugram set this rule in its batch order of 12 August 2021 (Complaint No. 4031 of 2019 and connected cases). The same order says holding charges cannot be charged ‘at any point of time’, electrification charges cannot be added at the offer of possession, and any other charge not in your agreement cannot be demanded. Before a valid offer, the builder must keep essential services running under Section 11(4)(d) of the RERA Act.

Updated 17 November 2026. We read the operative part of the 2021 batch order, two Haryana Real Estate Appellate Tribunal orders (November 2024 and September 2025) on holding charges, an HRERA Gurugram order of November 2024 on maintenance before an OC, and the model agreement for sale in the Haryana Real Estate Rules, 2017. No builder or project is named here: this is a method guide.

Can a builder charge maintenance before possession in Gurgaon?

Not before a valid offer. Section 11(4)(d) makes the promoter responsible for providing and maintaining essential services, on reasonable charges, until the association of allottees takes over. Clause 11 of the Haryana model agreement adds that the cost of that maintenance is included in the total price.

In a November 2024 order (Complaint No. 199 of 2024), HRERA Gurugram looked at common-area maintenance billed to buyers while no OC had been received and no valid offer made. It held the promoter liable to bear that cost. Maintenance becomes your bill once possession is validly offered or handed over.

At the offer of possession, HRERA allows advance maintenance at the rate in your agreement, capped at 12 months. The 2021 order explained that builders usually ask for 6 months to 2 years, and that a year is enough time for the residents’ association to form and take over.

What does HRERA allow for each line of the final demand?

These are the directions in paragraph 245 of the 12 August 2021 order. They apply to the agreement you signed. Where a heading is not in your agreement, the order says the builder cannot charge it.

  • Advance maintenance (AMC): allowed at the agreement rate at the offer of possession, but not for more than one year.
  • Holding charges: not payable at any time, even if the agreement has a clause. HRERA relied on Supreme Court Civil Appeal Nos. 3864–3889 of 2020, decided 14 December 2020. The Appellate Tribunal repeated this in orders dated 8 November 2024 and 1 September 2025.
  • IFMS (interest-free maintenance security): a reasonable amount is allowed. The builder must keep it in a separate bank account, give you details of the balance and interest on request, and cannot spend it on its own obligations under Section 14.
  • Increase in super area: chargeable only if the builder first gives you the details and justification. An unjustified demand is ‘liable to be quashed’.
  • Electrification charges: cannot be charged with the offer of possession, even if the agreement says otherwise.
  • Electricity, water and sewer connection charges: only the actual amount paid to the departments, shared pro rata by flat area, with proof and a computation given to you before you pay.
  • GST: if your due date of possession was before 1 July 2017, none. If later, GST is chargeable, but the builder must pass on the input-tax-credit benefit.
  • VAT: 1.05% for the period up to 31 March 2014; nothing for 1 April 2014 to 30 June 2017.
  • Club charges: payable if the club is running or will run within about 6 months; otherwise only after the club is completed.
  • Preferential location charges: payable as per the agreement, but refundable with interest if the unit stops being preferentially located.
  • Administrative or transfer charges: up to ₹15,000 for facilitating registration of the conveyance deed. Undefined ‘incidental’ or ‘miscellaneous’ charges cannot be charged.
  • Open car parking: cannot be charged. Covered parking under older agreements: only if the parking area is not already in your super area.
  • Interest on your late instalments: at the same prescribed rate the builder pays you for delay (Section 2(za)).

What changes for agreements signed after RERA?

The 2021 order dealt mostly with older ‘super area’ agreements. Agreements signed after the Haryana Rules of 28 July 2017 follow the model agreement in Annexure A, which adds three checks.

  • Price is on carpet area (clause 1.7). After the OC, the builder must confirm the final carpet area. If it shrinks, the excess is refunded within 90 days with interest. If it grows by up to 5%, the builder may bill the extra at your agreed rate per sq ft.
  • Taxes and levies (clause 1.2(ii)): any increase that comes after the scheduled completion date in the RERA registration, including any extension, cannot be charged to you.
  • Development charges (clause 1.3): a new or higher charge after that completion date cannot be passed on. For earlier increases, the builder must attach the notification to the demand.

Does an unreasonable demand make the offer of possession invalid?

It can. HRERA’s 2021 order lists three parts of a valid offer: it comes after the OC, the flat is habitable, and it is not accompanied by unreasonable demands outside the agreement. An offer that fails this test does not stop the builder’s delay liability. HRERA computes delay interest up to the valid offer plus two months, or actual handover if earlier. See HRERA Delay Interest Gurugram 2026: Rate & How to Calculate.

The order also says that where extra demands are made, buyers ‘may accept possession under protest or decline to take possession’ while objecting to them.

Worked example: checking a demand line by line

Illustrative figures only, not market rates. Take a 1,800 sq ft (super area) flat with a due date after July 2017. The final demand lists: advance maintenance for 24 months at ₹5 per sq ft per month, holding charges of ₹50,000, electrification charges of ₹1,20,000, and a super-area increase of 60 sq ft at ₹10,000 per sq ft.

  • Advance maintenance billed: 1,800 × ₹5 × 24 = ₹2,16,000. HRERA cap of 12 months: 1,800 × ₹5 × 12 = ₹1,08,000. Excess to question: ₹1,08,000.
  • Holding charges: ₹50,000 billed; ₹0 payable under the HRERA direction.
  • Electrification charges: ₹1,20,000 billed; ₹0 payable at the offer of possession under the HRERA direction.
  • Super-area increase: 60 × ₹10,000 = ₹6,00,000. Ask for the area calculation first. Without justification, HRERA says the demand is liable to be quashed.
  • Total under question in this example: ₹2,78,000 plus the ₹6,00,000 area demand until it is justified.

How do I dispute an item in the possession demand?

  • Write to the builder within the offer period. For each disputed line, ask for the agreement clause it relies on, the calculation, and the notification or departmental receipt behind it. The model agreement (clause 1.2(iii)) requires the builder to give details of taxes and levies with the notifications and dates.
  • Pay what is clearly due. If you want the keys while a dispute is open, pay the disputed part ‘under protest’ in writing.
  • Do not sign a blanket no-claim letter. HRERA’s 2021 order held that an indemnity-cum-undertaking signed to get possession does not stop you claiming delay interest. See Signing a Conveyance Deed Under Protest: HRERA's 2026 Rulings.
  • Keep to the clock: Section 19(10) expects you to take possession within two months of the OC. Act in writing within that window.
  • If the builder will not correct the demand, file a complaint with HRERA Gurugram. The fee is ₹1,000 plus ₹10 per annexure (Schedule III of the Haryana Rules). See How to File a Haryana RERA Complaint in Gurugram: Process, Fee and Documents.
  • For what monthly maintenance usually costs once you move in, see Maintenance Charges in Gurgaon 2026: Per Sq Ft Table and IFMS, EDC & Maintenance Charges in Gurgaon (2026): The Full Cost of a Flat. To budget the full possession-stage outgo (stamp duty, registry, deposits), use /calculators/gurgaon-total-cost.