Fit-out possession means the builder lets you into your flat before the occupation certificate (OC) so you can do interiors. It is a permission to work inside the flat, not possession in law. HRERA Gurugram held in Complaint No. 199 of 2024 (decided November 2024) that a fit-out offer made without an OC ‘is not a valid offer of possession’. It directed the promoter to hand over the flat within 60 days of getting a valid OC, and to pay delay interest until the offer made after the OC plus two months.
Updated 17 November 2026. We read that order, HRERA Gurugram’s 12 August 2021 batch order defining a valid offer of possession, Sections 11(4), 17, 18 and 19(10) of the RERA Act, and the Haryana model agreement for sale. This is a process guide; no builder or project is named.
What does fit-out possession mean?
Builders use phrases like ‘possession for fit-outs’ or ‘permission for interior works’. Typically the letter says construction is complete and the OC has been applied for, and invites you to start carpentry, modular kitchens or wardrobes while you wait. Sometimes a payment is asked for with it.
In law the question is simple: is this the ‘offer of possession’ that ends the builder’s delay period? In Gurugram the answer turns on the OC.
Can a builder give possession without an OC in Haryana?
- Section 11(4)(b) of the RERA Act makes the promoter responsible for getting the completion or occupancy certificate and making it available to buyers.
- Clause 7.2(B) of the Haryana model agreement says the promoter offers possession of a built-up unit after obtaining the OC, within three months of it.
- Clause 9.1 defines ‘ready to move in possession’ as a habitable flat, complete with agreed amenities, for which an OC has been issued.
- HRERA Gurugram’s 2021 batch order lists three parts of a valid offer: it comes after the OC, the flat is habitable, and there are no unreasonable demands outside the agreement.
- Complaint No. 199 of 2024 applied this test directly: a fit-out offer without an OC was held not to be a valid offer of possession.
What happens to delay interest if I accept fit-out possession?
It keeps running. In the 2024 order, HRERA directed interest at the prescribed rate (11.10% a year at that time) from the due date until the offer of possession after obtaining the OC plus two months, or actual handover, whichever is earlier. The two months come from Section 19(10), which gives a buyer two months from the OC to take possession. HRERA counts them from the date of the offer.
To estimate your figure, use HRERA Delay Interest Gurugram 2026: Rate & How to Calculate. For who qualifies, see Delay Compensation Haryana RERA: 2026 Rules for Gurugram.
Who pays maintenance during a fit-out period?
Section 11(4)(d) makes the promoter responsible for essential services, on reasonable charges, until the association of allottees takes over. In the 2024 order, a maintenance agency had billed common-area maintenance while no OC existed and no valid offer had been made. HRERA held the promoter liable to bear it.
Advance maintenance is due only with a valid offer of possession, and HRERA caps it at 12 months. Holding charges are not payable at any time under HRERA’s rulings.
Can I register the conveyance deed or move in?
Conveyance follows possession. Section 17 asks the promoter to execute a registered conveyance deed and hand over possession. Where no local law sets a period, the conveyance deed is due within three months of the OC. The Haryana model agreement asks for conveyance within 3 to 6 months of possession. In practice, expect the deed after the OC-backed offer, not during fit-out.
Living in the flat is a different step from doing interiors in it. The OC is the certificate that the building is fit to occupy, so plan to move in only after it is issued.
What should I insist on in writing before taking keys for fit-outs?
- A letter saying the keys are given only as permission for interior works, and that it is not an offer of possession under the agreement or the RERA Act.
- No maintenance, holding or other charges until a valid offer is made after the OC.
- An express statement that your right to delay interest under Section 18 is not affected.
- Who is responsible for damage to your interiors from ongoing building work, and for security of your materials.
- Rules for your contractors: working hours, debris removal, and any deposit (get the refund terms in writing).
- A commitment that the formal offer will follow with a copy of the OC (clause 7.2(B)).
- Photos and a snag list of the bare flat on the day you take keys, so later defects are not blamed on your interior work. Clause 12 of the model agreement excludes defects caused by the buyer’s own structural changes.
Should I accept a fit-out offer?
It can save you two or three months of interior time once the OC arrives. The risks: work may need redoing if services change, the building is still a construction site, and the OC date is not in your control. If you accept, keep the letter clearly limited, keep paying only what the agreement requires, and use the snag checklist in Flat Possession Checklist: Bangalore Snag List and Documents as a template for the bare-flat record. To see which towers already have an OC, start from Ready to Move in Gurgaon: 30 HRERA Rows With OC or CC (2026).