A commencement certificate (CC) is the planning authority's permission to start building after the plan is sanctioned. In Bengaluru it comes in two steps on the Greater Bengaluru Authority's building-permit portal: a First CC that allows work ‘upto plinth’, and, after the plinth is checked, a Further CC for the rest of the building. The portal's FAQ says the plinth CC is issued in 3 working days. For an apartment project, the RERA Act requires the promoter to file an authenticated copy of the approvals and the CC, phase by phase, so you can check it on Karnataka RERA before booking.

Updated 18 November 2026. We opened the GBA building-permit portal (bpas.bbmpgov.in) and its FAQ, Section 4 of the RERA Act, the Karnataka RERA home page, LA Bill No. 17 of 2025, a Cyril Amarchand Mangaldas note of 6 July 2026 on OC exemptions and a Deccan Herald report of 16 July 2025. The old BBMP CC service sheet did not load.

What is a commencement certificate, in plain terms?

  • Plan sanction says what you may build. The CC says you may now start building it.
  • The GBA portal's FAQ lists the stages of a building permit: Concession, Concession order, IOD, First CC, Further CC, BCC (building completion certificate) and OCC (occupancy certificate).
  • First CC: ‘Commencement Certificate will be issued online to start the work upto plinth.’
  • Plinth check: the FAQ says site inspection is carried out ‘only at the time of plinth checking and while issuing OC/BCC’.
  • Further CC: issued after the plinth check, for construction above plinth.
  • Validity: the FAQ says building permission granted is valid for one year.
  • Note: parts of this FAQ use terms (IOD, CTS number) from other cities' systems, and some answers conflict, for example on payment modes. Treat its timelines as indicative.

Commencement vs completion vs occupancy certificate

  • CC (start): permission to build, first up to plinth and then above it.
  • BCC (completion): the owner's or professional's certificate that the building is complete, submitted with a request for joint inspection, per the FAQ.
  • OC (occupy): permission to occupy the building, issued after inspection. The FAQ says part or full OCC/BCC is granted within 7 working days.
  • Why buyers care: a building started without a CC can still face penalties at the end. The fee rules reproduced in LA Bill No. 17 of 2025 include a penalty ‘for not obtaining commencement certificate at the commencement of the construction’, charged when the completion certificate is issued.
  • Full comparison of OC and completion certificates: Occupancy Certificate vs Completion Certificate in Bengaluru: What to Demand Before You Take Possession

How do you check a project's CC?

  • On Karnataka RERA: open rera.karnataka.gov.in → ‘Know Project Status’ (/viewAllProjects), find the project and open its documents. Section 4(2)(c) of the RERA Act requires the promoter to enclose ‘an authenticated copy of the approvals and commencement certificate from the competent authority’, and for a phased project, for each phase.
  • Match the phase: if you are buying in Tower C or Phase 2, look for the CC that covers that tower or phase, not just Phase 1's.
  • On the GBA portal: bpas.bbmpgov.in → Search → Citizen Search. The FAQ lists search fields: file number, name of applicant, name of architect or licensed surveyor, zone and ward. To view a CC, the FAQ says go to ‘First CC’ (or ‘FCC’), click ‘Approved’ and select the file.
  • Ask the builder for the plan sanction (LP) number and the CC numbers. They should match the RERA uploads and the portal record.
  • Plan approval check: How to Check Building Plan Approval Online in Bangalore and Nambike Nakshe 2.0: 30-Minute Building Plan Approval (2026)
  • Example RERA-registered projects in our catalogue to practise on: Godrej Regent Park and Sattva Bhumi

How do you get a CC for your own house, and what does it cost?

  • Your architect or licensed surveyor files online on bpas.bbmpgov.in. The FAQ's eight-step list includes ‘Online Application for Commencement Certificate upto plinth level’ and ‘Issue of Commencement Certificate after duly paying the requisite charges’.
  • e-Khata first: the portal's notice says e-khata is mandatory for building licence, plinth certificate and OC applications from 1 July 2025. See e-Khata guide, Bangalore
  • Fees: the scrutiny fee is paid with the application, and other fees follow ‘as per the demand note generated at various stages’ (FAQ).
  • Fee ceiling: the BBMP Act, 2020 provisions reproduced in LA Bill No. 17 of 2025 cap the CC fee at 0.20% of the guidance value of the vacant site multiplied by the proposed plinth area. The Bill proposed residential ceilings at two-thirds of those values; check the rate on your demand note.
  • Worked example (ceiling, illustrative): guidance value ₹4,000 per sq ft and plinth area 1,000 sq ft → 0.20% × ₹4,000 × 1,000 = ₹8,000. At two-thirds for residential use, ₹5,333.
  • Outside GBA limits, approvals come from the local planning authority or gram panchayat; see BMRDA Approved Layout List: All Bangalore Planning Authorities

Did the 2025–26 exemptions remove the need for a CC?

Not that we could confirm. The exemptions are about the occupancy certificate. Notification NAE/334/MNU/2025 of 9 September 2025 exempted residential buildings on plots up to 1,200 sq ft (ground plus two, or stilt plus three) in GBA limits from the OC, and an Urban Development Department order of 5 June 2026 widened this to plots up to 2,400 sq ft (20% tolerance) and ground plus three floors, according to Cyril Amarchand Mangaldas. The same note says building plan approval is still mandatory before construction, whatever the size. Some news reports in 2025 said small buildings would also be spared the CC, but we found no notification saying so. More: OC Exemption in Bangalore 2026: Buying a House Without an OC