Seven HRERA registrations in Sector 93, Gurgaon (villages Wazirpur and Hayatpur) carry completion dates in 2027: Kashi plots (11 January), Ashiana Amarah Phase I and IA (15 January), Aanandam Ora plots (31 March), Signature Global City 93 (28 April and 30 November), DLF's Gardencity Enclave floors (19 August) and Ashiana Amarah Phase II (15 October). Ashiana Amarah Phase I and IA already shows an occupation-certificate record on the HRERA register.
Updated 20 November 2026. We read every Sector 93 row on the HRERA Gurugram register, noted the ‘Registration up to’ date and the OC/CC/PCC link, and opened the HRERA forms for unit counts. Portal dates that differ are named. Sector guide: Sector 93 Gurgaon, Gurgaon
Sector 93 Gurgaon projects due in 2027: summary
Ordered by HRERA completion date. Format: project — format — HRERA no. — HRERA completion — OC record.
- Kashi (Jai Ganga Realtech) — plots, Sectors 89 and 93 — RERA-GRG-2013-2025 — 11 Jan 2027 — none yet
- Ashiana Amarah Phase I and IA — apartments — RERA-GRG-1058-2022 — 15 Jan 2027 — OC/CC/PCC record uploaded
- Aanandam Ora (Ora Land and Housing) — plots — RERA-GRG-1340-2023 — 31 Mar 2027 — none yet
- Signature Global City 93 — DDJAY plots and floors — RERA-GRG-1281-2023 — 28 Apr 2027 — none yet
- Independent Floors at DLF Gardencity Enclave — floors — RERA-GRG-1060-2022 — 19 Aug 2027 — none yet
- Ashiana Amarah Phase II — apartments — RERA-GRG-1249-2022 — 15 Oct 2027 — none yet
- Signature Global City 93 (second registration) — DDJAY plots and floors — RERA-GRG-1283-2023 — 30 Nov 2027 — none yet
Kashi, Sectors 89 and 93
RERA-GRG-2013-2025, certificate GGM/977/709/2025/80 dated 27 August 2025, Jai Ganga Realtech LLP, on Badha and Hayatpur land. HRERA completion: 11 January 2027. Our page: Kashi
Ashiana Amarah Phase I and IA, Sector 93
RERA-GRG-1058-2022, certificate GGM/590/322/2022/65 dated 18 July 2022, Ashiana Housing, village Wazirpur. The HRERA form lists 224 apartments of 92.90, 111.95 and 130.81 sq m carpet (about 1,000, 1,205 and 1,408 sq ft) plus 136 small units, on 5.04 acres of a 22.1-acre licence. HRERA completion: 15 January 2027. The register row shows an OC/CC/PCC record, so ask Ashiana which towers it covers. Housiey lists ‘Ashiana Amarah’ with April 2029 possession, which matches a later phase, not this one. Our page: Ashiana Amarah
Aanandam Ora, Sector 93
RERA-GRG-1340-2023, certificate GGM/711/443/2023/55 dated 17 April 2023, Ora Land and Housing Pvt Ltd, a plotted project. HRERA completion: 31 March 2027. Our page: Orris Aanandam Ora
Signature Global City 93, Sector 93
Two registrations dated 30 January 2023 by Signature Builders on Wazirpur land. RERA-GRG-1281-2023 covers 251 plots, 141 of them about 150 sq m, on 17.32 acres, with HRERA completion on 28 April 2027. RERA-GRG-1283-2023 runs to 30 November 2027. Portals give one date for the whole project (from June 2026 to December 2027); the date that applies to you depends on which registration your floor is in. Our page: Signature Global City 93
Independent Floors at DLF Gardencity Enclave, Sector 93
RERA-GRG-1060-2022, certificate GGM/603/335/2022/78 dated 17 August 2022, DLF Ltd as collaborator under licence 94 of 2021. The form covers 97 plots of 132.6 to 150 sq m on 3.57 acres for floors. HRERA completion: 19 August 2027. The wider DLF Gardencity Enclave colony (RERA-GRG-1008-2022, 367 plots on 26.92 acres) is registered to 30 October 2028 and already shows an OC/CC/PCC record; Phase 2 floors (RERA-GRG-1223-2022) are also due 30 October 2028. Our pages: Independent Floors At DLF Gardencity Enclave and DLF Garden City Enclave
Ashiana Amarah Phase II, Sector 93
RERA-GRG-1249-2022, certificate GGM/685/417/2023/29 dated 2 February 2023, Ashiana Housing, Wazirpur revenue estate. HRERA completion: 15 October 2027. Our page: Ashiana Amarah
Which Sector 93 projects come after 2027?
- Orchard Avenue 3, Signature Builders — RERA-GRG-1486-2023 — 31 July 2028
- Ashiana Amarah Phase 3 and 3A — RERA-GRG-1440-2023 — 16 October 2028
- DLF Gardencity Enclave and its Phase 2 floors — RERA-GRG-1008-2022 and 1223-2022 — 30 October 2028
- Ashiana Amarah Phase 4 — RERA-GRG-1594-2024 — 30 April 2029
- Ashiana Amarah Phase 6 — RERA-GRG-1909-2025 — 30 April 2029
- Ashiana Amarah Phase 5 — RERA-GRG-1753-2024 — 31 January 2030
Which Sector 93 projects are already ready to move?
The HRERA register shows OC/CC/PCC records for Signature Global's Orchard Avenue (RERA-GRG-352-2019) and Orchard Avenue 2 (RERA-GRG-238-2019), and for Pyramid's The Balcony (RERA-GRG-245-2019), alongside Ashiana Amarah Phase I and IA. For a wider list across New Gurgaon see Ready to Move Flats in New Gurgaon: 18 OC Projects (Nov 2026)
What is near Sector 93: Sectors 92 and 95?
- Sector 95 (Dhorka): Signature Global Superbia, RERA-GRG-767-2020, due 29 December 2026 — Signature Global Superbia; Signature Global Aspire, RERA-GRG-322-2019, due 28 April 2027 — Signature Global Aspire
- Sector 92: Signature Global City 92 — Signature Global City 92; sector page Sector 92 Gurgaon, Gurgaon
- All New Gurgaon dates for 2027: New Gurgaon Possession 2027: 54 HRERA Dates by Sector. Buyer's guide to the sector: Sector 93 Gurgaon: Buyer's Guide 2026 — Prices, Projects and Connectivity. NRI view: Sector 93 Gurgaon
How do the Ashiana Amarah phases differ?
Ashiana has registered Amarah in six parts, each with its own HRERA number and date. Phase I and IA, the first, covers 5.04 acres of a 22.1-acre licence: 112 homes of 92.90 sq m carpet (about 1,000 sq ft), 56 of 111.95 sq m (about 1,205 sq ft) and 56 of 130.81 sq m (about 1,408 sq ft). Phase II follows nine months later on HRERA (15 October 2027), then Phases 3 and 3A (October 2028), 4 and 6 (April 2029) and 5 (January 2030). A resale or new booking is tied to one of these numbers; the date on your agreement comes from that registration, not from the project name.
Sector 93 and nearby prices: what do portals show?
No builder price for the 2027 projects above could be verified today. Square Yards' New Gurgaon ready-to-move list (approx, portal, opened 20 November 2026) gives these nearby reference points for registered projects:
- Orchard Avenue 2, Sector 93 (RERA-GRG-238-2019): 2 BHK of 617–680 sq ft from about ₹59.85 lakh, ₹9,700 per sq ft
- Signature Global Superbia, Sector 95 (RERA-GRG-767-2020): 2 BHK of 673–681 sq ft from about ₹97.95 lakh, ₹14,554 per sq ft
- The Roselia, Sector 95A (RERA-GRG-384-2019): 2 BHK of 800–970 sq ft from about ₹88.80 lakh, ₹11,100 per sq ft
- DLF Garden City Independent Floors, Sector 92: 4 BHK of 2,864–3,480 sq ft from about ₹6.30 crore, ₹22,000 per sq ft
How do I check a Sector 93 project's possession date on HRERA?
- Search the RERA-GRG number (not just the name) on the HRERA Gurugram register; Ashiana Amarah has six separate registrations and City 93 has two.
- Read ‘Registration up to’ for the registered completion date and click ‘View OC/CC/PCC’ if it appears.
- Open the form to confirm whether you are buying an apartment, a floor or a plot.
- Compare with your agreement's possession clause; for the delay-interest rules see HRERA Delay Interest Gurugram 2026: Rate & How to Calculate