When a Gurgaon developer wants to change the sanctioned layout or building plans of a licensed project, DTCP Haryana first grants only an ‘in-principle’ approval. The developer must then publish a public notice in at least three national newspapers (one in Hindi) within 10 days, write to every existing allottee by registered post, and put the old and revised plans on its website and at the site office. Allottees get 30 days to file objections with the Senior Town Planner, Gurugram. Separately, RERA section 14(2) needs written consent from at least two-thirds of allottees for such changes.

Updated 17 November 2026. We read the state’s directions of 25 January 2021 on plan revisions, DTCP’s office order of 5 November 2020, a DTCP in-principle approval letter of 11 August 2023, the 18 February 2015 policy on change in beneficial interest, and RERA sections 14 and 15.

What does a DTCP public notice for revised plans contain?

Under the state’s 25 January 2021 directions, issued under RERA section 83 and section 9A of the 1975 licensing Act, the in-principle approval carries these conditions:

  • Advertisement in at least three national newspapers widely circulated in the district, one in Hindi, within 10 days of the in-principle approval
  • Registered post to each existing allottee within two days of the advertisement, giving the last date for objections, with a copy to the Senior Town Planner
  • A certified list of all existing allottees filed with the Senior Town Planner’s circle office
  • Earlier and revised plans hosted on the developer’s website and displayed at the site office, with a certificate from the Senior Town Planner that this was done
  • 30 days for allottees to file objections at the Senior Town Planner’s office, where both plans must be available to see
  • No advertisement for booking or sale of the changed space until final approval

What happens after allottees object?

The Senior Town Planner examines the objections, hears the developer and the objectors, and sends a recommendation to the competent authority within 90 days of the advertisement. The authority ‘may decide to make amendments’ to the plan, which bind the developer. The developer must also file a report of objections received and action taken, with an undertaking that allottees’ rights are not infringed. Only then is the ‘provisional’ plan given final approval with a sanction letter. A DTCP letter of 11 August 2023 for a Gurugram commercial project follows exactly this sequence.

If the developer files an affidavit that no third-party rights have been created, the registered-post step is dropped, but the public notice is still required.

Yes, these are two different tests. RERA section 14(2)(ii) bars changes to the building or common-area plans without the previous written consent of at least two-thirds of the allottees, other than the promoter. Several bookings by one person, family or group company count as one allottee. Section 14(2)(i) separately bars changes to your own unit’s plan and specifications without your consent, except minor changes needed for structural or architectural reasons after declaration to you.

DTCP’s office order of 5 November 2020 said no revision would be allowed without meeting section 14, and that final approval would need two-thirds consent. The 2021 directions then set the objection procedure above. In practice, keep both in mind: object at DTCP within 30 days, and do not sign a consent form you have not read against the revised drawings.

What is a change in beneficial interest or change of developer?

Under DTCP’s policy of 18 February 2015, a ‘change in beneficial interest’ covers a new developer, assignment of joint development or marketing rights, or a cumulative change in shareholding of more than 25%. It needs the Director General’s prior approval and administrative charges of 25% of the licence fee. Where third-party rights exist, objections are invited from allottees through a public notice and by registered post. The new entity must take on all liabilities of the old developer and settle pending allottee issues.

RERA section 15 adds that a promoter cannot transfer majority rights and liabilities in a project without prior written consent of two-thirds of allottees and the Authority’s prior written approval. The transfer does not affect existing allotments, and the new promoter gets no extra time to finish the project.

How do I file an objection?

  • Note the last date in the newspaper notice or your registered letter; 30 days run from publication
  • Compare the old and revised plans at the developer’s site office or the Senior Town Planner, Gurugram; photograph the changed sheets
  • Write a dated objection: your unit number, allotment date, the exact change you object to (tower added, park reduced, entry shifted) and why it affects you
  • Submit it at the Senior Town Planner’s office and keep a stamped acknowledgement; send a copy to the developer
  • Attend the hearing, and ask for the decision in writing
  • If changes go ahead without the consent RERA requires, you can complain to HRERA Gurugram through its portal

Before you book, read the project’s sanctioned plan on its HRERA page and ask in writing whether any revision is pending. Our checks for licences and registrations are at How to Verify a DTCP Licence and HRERA Registration in Gurgaon, Step by Step and Gurgaon Project Paper Checks 2026: OC, CC, DTCP and RERA. Newly registered projects are at New Hrera Registrations, Gurgaon; compare sectors at Sectors, Gurgaon.