In Bengaluru, rainwater harvesting is compulsory under Section 72A of the Bangalore Water Supply and Sewerage Act, 1964. As rewritten in October 2021, it applies to anyone building on a site of 108 sq m (about 1,163 sq ft) or more, which covers a 30x40 site. It also applies to existing buildings on sites of 216 to 1,000 sq m (about 2,325 to 10,764 sq ft), which covers a 40x60 site. Sites of 1,000 sq m and above also need dual piping. If you don't comply, BWSSB adds a penalty to your water bill.

Updated 18 November 2026. We read the amended Section 72A in the Karnataka Gazette copy that BWSSB publishes, the BWSSB circular that applied it, BWSSB's rainwater harvesting page and brochure, and recent reports on the penalty. Many pages that rank for this search still quote the older 2,400 and 1,200 sq ft limits. Those come from the 2009 version of the law, which the 2021 Act replaced.

Who must install rainwater harvesting in Bangalore?

Karnataka Act No. 29 of 2021, the Bangalore Water Supply and Sewerage (Amendment) Act, 2021, substituted Section 72A. It received the Governor's assent on 5 October 2021, was published on 7 October 2021 and came into force at once (Karnataka Gazette, as hosted by BWSSB). BWSSB told its engineers to enforce it by a circular dated 20 December 2021.

  • New buildings on sites of 108 sq m or more: a structure for storage, for use or for groundwater recharge, as the Board's regulations and guidelines provide. A 30x40 site (111.5 sq m) is covered.
  • Existing buildings on sites of 216 to 1,000 sq m without RWH before the 2021 Act: storage, use and groundwater recharge. A 40x60 site (223 sq m) is covered.
  • Sites of 1,000 sq m and above, new or existing: dual piping plus RWH for storage and for uses other than drinking, cooking and bathing. Storage is based on roof area, and recharge on paved and unpaved areas.
  • The Act defines RWH as collecting rain from the roof or vacant land for use or recharge. 'Groundwater recharge' includes recharging an open well or a borewell.

What did the old rule say, and why do pages still quote it?

The 2009 version, in force from August 2009, covered existing buildings on sites of 2,400 sq ft and above and new buildings on 1,200 sq ft and above in BBMP limits (Prajavani, 14 June 2021, clipping on the BWSSB site). BWSSB's web page still says 60x40 for existing buildings and 30x40 for new ones. In practice the 2021 thresholds are close: 108 sq m is about 1,163 sq ft and 216 sq m about 2,325 sq ft. The real changes are the 1,000 sq m upper band for retrofits and the dual-piping rule for large sites.

What is the BWSSB penalty for not having rainwater harvesting?

The penalty is added to the water bill. Sources disagree on the rate, so check your own bill.

  • Residential: 25% of the water bill for the first three months, then 50%. Prajavani's example: on a ₹100 bill, an owner pays ₹125 at first, and 50% extra if the system is still missing later (14 June 2021, hosted by BWSSB). Citizen Matters (7 December 2023) and PropNewz (7 October 2026) give the same 25% then 50%.
  • Non-residential: 50%, then 100% (Citizen Matters, 7 December 2023).
  • Conflict: some news reports give 50% then 100% for homes. We found no BWSSB tariff notice online today that settles it, so the 25%/50% figure rests on the clipping BWSSB itself publishes and two news reports.
  • Scale: 39,703 defaulting properties paid ₹1.95 crore in penalties in October 2023, about ₹491 each (Citizen Matters). In 2021, about 56,000 owners were being fined, more than ₹1.5 crore a month (Prajavani).
  • If the owner does not build it, the Board may build the structure and recover the cost as arrears of land revenue (PropNewz, 7 July 2026).

How much does rainwater harvesting cost in Bangalore?

  • BWSSB brochure, 60x40 site, roof water to a recharge dug well (4 ft diameter, 25 ft deep with RCC rings): ₹80,442 plus 10% contractor profit = ₹88,486. The dug well alone is ₹50,000.
  • BWSSB brochure, storage route: pipes ₹16,042, filter and fitting ₹9,750, labour ₹6,400, transport ₹1,500, plus a 4,000-litre sump at ₹6 per litre (₹24,000) and 10% profit = ₹63,461.
  • Officials quoted in 2021: ₹6,000–7,000 for a 30x40 house that already has a sump, and ₹15,000–16,000 for a recharge pit; private agencies were charging more than ₹30,000 (Prajavani, approx).
  • An expert quoted in 2023: as little as ₹5,000, or up to ₹15,000 with a good filter, if no new sump is needed (Citizen Matters, approx).
  • The brochure says its prices are at market rates of the day; it carries no date, so treat them as a guide.

What does a system need?

  • Catchment: a flat RCC roof sloped to the outlet, or a sloped roof with gutters (BWSSB brochure).
  • Pipes and a filter: a sand-bed filter or a wall-mounted filter; BWSSB does not recommend any particular brand (BWSSB brochure).
  • Storage, recharge or both: a sump or tank, a recharge well, or both.
  • Sizing: PropNewz reports a BWSSB guideline of 20 litres per sq m of roof plus 10 litres per sq m of paved area. We could not find this on a BWSSB page today, so ask the engineer to size it.
  • Help: BWSSB's Sir M. Visvesvaraya Rain Water Harvesting Theme Park shows working systems.

How do you prove compliance to BWSSB?

For a new water connection, owners upload photographs of the RWH pipes and filter on BWSSB's website, and officials may inspect (Citizen Matters, 7 December 2023). We found no separate RWH certificate service on the BWSSB site today. Keep the photographs and your bills, which show whether a penalty is being charged. The new-connection process: BWSSB Water Connection Apply Online Bangalore: Steps, Charges.

Rainwater harvesting in apartments: what buyers should check