We list 31 Gurgaon projects with HRERA registered completion dates between 29 February 2032 and 31 December 2034: nine in 2032, sixteen in 2033 and six in 2034. Most are 2025–26 launches on Golf Course Extension Road, Golf Course Road, the Southern Peripheral Road and the Dwarka Expressway, including Oberoi Three Sixty North and Godrej Verano (2033) and Pioneer Alura (2034).

Updated 20 November 2026. Each date is the ‘Registration up to’ value on the HRERA Gurugram register, read today, with the HRERA number beside it. Where a portal or builder shows a different date we say so. This is a selection of residential projects buyers search for, not every registration.

Gurgaon projects with possession 2032–2034: summary

Ordered by HRERA completion date. Format: project — sector — HRERA no. — HRERA completion.

  • M3M Residences by Elie Saab — 111 — RERA-GRG-2048-2025 — 29 Feb 2032
  • Birla Pravaah — 71 — RERA-GRG-2071-2025 — 31 Mar 2032
  • Smartworld Sky Arc — 69 — RERA-GRG-1723-2024 — 31 May 2032
  • Godrej Sora — 53 — RERA-GRG-1967-2025 — 30 Sep 2032
  • Trump Residences Gurgaon — 69 — RERA-GRG-1850-2025 — 30 Sep 2032
  • Lodha Pantheon — 28 — RERA-GRG-2299-2026 — 30 Nov 2032
  • Experion The Trillion — 48 — RERA-GRG-1773-2024 — 31 Dec 2032
  • Omara by Trehan IRIS — 80 — RERA-GRG-2092-2025 — 31 Dec 2032
  • Cocoa County Phases 02–04 — 88A — RERA-GRG-2239/2270/2271-2026 — 31 Dec 2032
  • Tonino Lamborghini Residences — 71 — RERA-GRG-2186-2026 — 1 Jan 2033
  • Sobha Crescent Phase 1 — 63A — RERA-GRG-2185-2026 — 31 Mar 2033
  • DLF Privana Enclave (plots) — 76/77 — RERA-GRG-2236-2026 — 30 Apr 2033
  • The Aerth — 79 — RERA-GRG-2231-2026 — 30 Apr 2033
  • Godrej Verano — 63A — RERA-GRG-2274-2026 — 2 Jun 2033
  • Riviera at AIPL Lake City — 103 — RERA-GRG-2085-2025 — 30 Jun 2033
  • Smartworld Nature's Court I — GIC, M9–M11 — RERA-GRG-2126-2025 — 30 Jun 2033
  • Birla Arika Phase 2 — 31 — RERA-GRG-2142-2025 — 9 Jul 2033
  • The Estate One — 63A — RERA-GRG-2197-2026 — 21 Jul 2033
  • Godrej Samaris — 53 — RERA-GRG-2216-2026 — 31 Aug 2033
  • The Oryza — 88A — RERA-GRG-2158-2026 — 30 Sep 2033
  • Max Estates Estate 361 — 36 (Harsaru) — RERA-GRG-2093-2025 — 30 Sep 2033
  • Ashiana Aaroham Phase II — 80 — RERA-GRG-2134-2025 — 31 Oct 2033
  • DLF The Aureva — 63 — RERA-GRG-2265-2026 — 31 Oct 2033
  • Tulip Melrose — 70 — RERA-GRG-2082-2025 — 31 Dec 2033
  • Oberoi Three Sixty North (Towers A, B, C, E, F, G) — 58 — RERA-GRG-2240-2026 to 2245-2026 — 31 Dec 2033
  • Pioneer Alura — 62 — RERA-GRG-2049-2025 — 1 Jan 2034
  • Aquaria at AIPL Lake City — 103 — RERA-GRG-2207-2026 — 31 Mar 2034
  • Pardos Sakura — 90 — RERA-GRG-2307-2026 — 13 May 2034
  • M3M Forestia West I and East I — GIC, M9–M11 — RERA-GRG-2124-2025 and 2125-2025 — 30 Jun 2034
  • DLF Privana North — 76/77 — RERA-GRG-1781-2024 — 30 Sep 2034
  • Experion One42 — 42 — RERA-GRG-1765-2024 — 31 Dec 2034

Why do new Gurgaon launches carry 2032–2034 completion dates?

The dates are long because the buildings are tall and the schedules are declared conservatively. Trump Residences has two 51-storey towers, Tonino Lamborghini Residences five 41-floor towers and Riviera two 43-floor towers. HRERA forms show the full span: Aquaria's construction runs from 1 October 2026 to 31 March 2034, and County Group gives 1 July 2026 to 31 December 2032 for Cocoa County.

Seasonal air-quality rules also take working days out of each winter. Haryana's release of 3 November 2026 records that the Commission for Air Quality Management stopped dust-generating construction across NCR from 5 to 20 November 2026, alongside the revised GRAP of 29 September 2026. Builders plan for such windows. See GRAP Construction Ban Gurgaon 2026: Possession Dates

Completion date vs possession offer: which one binds?

The HRERA date is the completion period the promoter declared under Section 4(2)(l)(C) of the RERA Act. Your possession date is in your agreement for sale, and that is the date Section 18 uses. After the occupation certificate, Section 19(10) asks the buyer to take physical possession within two months. If a builder's brochure shows an earlier year (Godrej's Verano page shows March 2031), treat it as a target.

M3M Residences by Elie Saab, Sector 111

RERA-GRG-2048-2025, registered 16 October 2025. HRERA completion: 29 February 2032; the form's proposed date is 30 September 2032. 336 apartments in three towers. M3M Residences by Elie Saab

Birla Pravaah, Sector 71

RERA-GRG-2071-2025, registered 6 November 2025 by Birla Estates on the Southern Peripheral Road. HRERA completion: 31 March 2032. Birla Pravaah

Smartworld Sky Arc, Sector 69

RERA-GRG-1723-2024, registered 11 October 2024 (promoter Riverday Infrastructure). HRERA completion: 31 May 2032. Smartworld Sky Arc

Godrej Sora, Sector 53

RERA-GRG-1967-2025, registered 25 August 2025 on plot GH-21, Golf Course Road. HRERA completion: 30 September 2032. Godrej Sora

Trump Residences Gurgaon, Sector 69

RERA-GRG-1850-2025, registered 13 March 2025 (promoter Riverday Infrastructure). 298 homes in two 51-storey towers on 11.7 acres; structural work began in March 2026 (Realty Today, 9 March 2026). HRERA completion: 30 September 2032. Realty Hunting notes listings showing 30 April 2033; the register shows 30 September 2032. Trump Residences Gurgaon

Lodha Pantheon, Sector 28

RERA-GRG-2299-2026, registered 11 September 2026 as ‘Lodha Golf Course Road’ and renamed Pantheon on 6 November 2026. 42 units of 237–814 sq m carpet. HRERA completion: 30 November 2032.

Experion The Trillion, Sector 48

RERA-GRG-1773-2024, registered 11 February 2025 on plot GH3. HRERA completion: 31 December 2032. Experion The Trillion

Omara by Trehan IRIS, Sector 80

RERA-GRG-2092-2025, registered 22 January 2026 (promoter Trehan Promoters & Builders). HRERA completion: 31 December 2032. Trehan IRIS Omara

Cocoa County, Sector 88A

Phases 02, 03 and 04 (RERA-GRG-2239-2026, 2270-2026, 2271-2026), registered 11 September 2026. County Group: 844 residences in nine towers on about 24 acres. HRERA completion: 31 December 2032 for all three. Cocoa County

Tonino Lamborghini Residences, Sector 71

RERA-GRG-2186-2026, registered 8 April 2026 by Signatureglobal (India). 812 residences over two phases in five 41-floor towers on about 12.4 acres; Phase 1 sold out (Construction World, 2 November 2026). HRERA completion: 1 January 2033. Tonino Lamborghini Residences Gurugram

Sobha Crescent Phase 1, Sector 63A

RERA-GRG-2185-2026, registered 3 April 2026: 336 apartments in two towers on 4.96 acres. HRERA completion: 31 March 2033. SOBHA Crescent

DLF Privana Enclave, Sectors 76/77

RERA-GRG-2236-2026, registered 23 July 2026, a plotted phase inside DLF's Privana township. HRERA completion: 30 April 2033. DLF Privana Enclave

The Aerth, Sector 79

RERA-GRG-2231-2026, registered 2 July 2026 by Boxacres Developers in village Naurangpur. HRERA completion: 30 April 2033. Aura The Aerth

Godrej Verano, Sector 63A

RERA-GRG-2274-2026, registered 11 August 2026: 630 apartments, from ₹4.91 crore (Godrej). HRERA completion: 2 June 2033; Godrej's page shows possession March 2031 and the form a likely completion of 31 August 2033. Godrej Verano

Riviera at AIPL Lake City, Sector 103

RERA-GRG-2085-2025, registered 8 December 2025: 344 apartments in two 43-floor towers. HRERA completion: 30 June 2033. AIPL Riviera at Lake City

Smartworld Nature's Court I, Gurgaon International City

RERA-GRG-2126-2025, registered 2 January 2026 (promoter Svabhumi Realtors) in Sectors M9–M11, Manesar. HRERA completion: 30 June 2033. Smartworld Nature's Court

Birla Arika Phase 2, Sector 31

RERA-GRG-2142-2025, registered 25 February 2026. HRERA completion: 9 July 2033. Phase 1 (RERA-GRG-1823-2024) is due 9 December 2031; Housiey shows a single January 2032 date. Birla Arika

The Estate One, Sector 63A

RERA-GRG-2197-2026, registered 20 August 2026 by Anant Raj. HRERA completion: 21 July 2033. Anant Raj The Estate One

Godrej Samaris, Sector 53

RERA-GRG-2216-2026, registered 4 May 2026 on plot GH-24. HRERA completion: 31 August 2033. Godrej Samaris

The Oryza, Sector 88A

RERA-GRG-2158-2026, registered 24 February 2026 (promoter Aura Builders and Developers). HRERA completion: 30 September 2033. The Oryza

Max Estates Estate 361, Sector 36 (Harsaru)

RERA-GRG-2093-2025, registered 21 November 2025 by Max Estates Gurgaon Two on village Harsaru land; HRERA records the sector as 36, while marketing uses 36A. HRERA completion: 30 September 2033. Max Estate 361

Ashiana Aaroham Phase II, Sector 80

RERA-GRG-2134-2025, registered 27 January 2026 on HSIIDC plot GH-04. HRERA completion: 31 October 2033, the same as Phase 1 (RERA-GRG-2020-2025). Ashiana Aaroham

DLF The Aureva, Sector 63

RERA-GRG-2265-2026, registered 14 September 2026 by DLF Home Developers, a senior-living project. HRERA completion: 31 October 2033. DLF The Aureva

Tulip Melrose, Sector 70

RERA-GRG-2082-2025, registered 7 November 2025 (promoter Premium Infratech). HRERA completion: 31 December 2033. Tulip Melrose

Oberoi Three Sixty North, Sector 58

Six tower registrations, RERA-GRG-2240-2026 to 2245-2026, dated 26 June 2026. Phase 1 has 832 homes in six towers on 14.8 acres at a ₹35,000 per sq ft basic price (ThePrint/PTI, 6 July 2026). HRERA completion: 31 December 2033 for each tower. Oberoi Three Sixty North

Pioneer Alura, Sector 62

RERA-GRG-2049-2025, registered 16 October 2025. Pioneer targets Q2 2031; HRERA completion: 1 January 2034. Pioneer Alura

Aquaria at AIPL Lake City, Sector 103

RERA-GRG-2207-2026, registered 5 June 2026. HRERA completion: 31 March 2034. Aquaria at AIPL Lake City

Pardos Sakura, Sector 90

RERA-GRG-2307-2026, registered 2 November 2026 by Pardos Craft Homes in village Hayatpur. HRERA completion: 13 May 2034. Pardos Sakura

M3M Forestia West I and East I, Gurgaon International City

RERA-GRG-2124-2025 (2 January 2026) and RERA-GRG-2125-2025 (21 January 2026), both in Sectors M9–M11, Manesar. HRERA completion: 30 June 2034 for both. M3M Forestia West and M3M Forestia East

DLF Privana North, Sectors 76/77

RERA-GRG-1781-2024, registered 5 June 2025. HRERA completion: 30 September 2034. DLF Privana North

Experion One42, Sector 42

RERA-GRG-1765-2024, registered 16 December 2024 on plot GH-1, Golf Course Road. HRERA completion: 31 December 2034. Experion One42

Are Godrej Miraya and Godrej Astra due in 2032?

No. Portal snippets put them in 2032, but the HRERA register shows Godrej Miraya (RERA-GRG-1698-2024) on 30 September 2031 and Godrej Astra (RERA-GRG-1725-2024) on 16 October 2031. Both are in Gurgaon Projects Possession 2030: HRERA List for 2029–2031

How do I verify a 2032–2034 possession date on HRERA?

  • Search the RERA-GRG number on the HRERA Gurugram register and read ‘Registration up to’.
  • For multi-tower projects such as Oberoi, check the number for your own tower; each tower can carry its own registration.
  • Open the form for the construction start and likely completion dates, and the quarterly progress report for work done.
  • Match all of these with the possession clause and the delay-interest clause in your agreement. Paper checks: Gurgaon Project Paper Checks 2026: OC, CC, DTCP and RERA. Index of builders and RERA data: /rera-index