GMDA now supplies about 770 MLD of drinking water to Gurugram: roughly 500 MLD from the Chandu Budhera treatment plant and 270 MLD from Basai (GMDA, 20 October 2026). That is up from about 670 MLD in July and 720 MLD in September 2026. Two approved projects would add 100 MLD each: Basai Unit 4 (₹149 crore, 30 months, approved July 2026) and a sixth unit at Chandu Budhera (24 months from allotment, approved 20 October 2026).

Updated 8 November 2026. Every figure below is from a dated GMDA press release on gmda.gov.in. We list them in order so the changes are clear.

Gurugram's water figures, release by release

  • 8 June 2026 — Basai supplies 270 MLD; GMDA clears space in the 76-acre Basai campus for a 100 MLD Unit IV and says the tender is floated.
  • 20 July 2026 — Total supply about 670 MLD. Basai: three filtration units, 270 MLD, storage about 1,385 million litres. Chandu Budhera: four 100 MLD units, 400 MLD, storage about 1,615 million litres. Basai Unit 4 approved by the High Powered Works Purchase Committee chaired by the Chief Minister: 100 MLD plus two 300-million-litre tanks, ₹149 crore, 30 months.
  • 29 September 2026 — About 720 MLD supplied; 770 MLD after the Sector 72 boosting station is commissioned (planned October). Basai Unit 4 work awarded.
  • 5 October 2026 — Groundwater plan: departments to phase out borewells; 142 ponds planned for rejuvenation in the district (68 done, 74 under way, per the Haryana Water Resources Authority); 10 MLD of treated water already goes to the textile industry.
  • 20 October 2026 — About 770 MLD: roughly 500 MLD from Chandu Budhera and 270 MLD from Basai. A sixth 100 MLD unit at Chandu Budhera approved for Sectors 81–115 and the Dwarka Expressway area, on 15 acres inside the plant, targeted within 24 months of allotment. GMDA is planning water supply up to 2051.

Where the next 200 MLD would come from

  • Basai Unit 4: treatment from 270 to 370 MLD; storage to nearly 2,000 million litres; 30 months from July 2026 approval.
  • Chandu Budhera unit 6: a further 100 MLD; 24 months from allotment of the work.
  • On GMDA's own unit counts, the two plants would have about 970 MLD of treatment capacity once both are built (Basai 370 plus six 100 MLD units at Chandu Budhera). This is a sum of announced units, not a forecast of supply.
  • Note on Chandu Budhera: GMDA's July release listed four operational units (400 MLD); its October release calls the new unit the sixth and gives about 500 MLD of supply from the plant, so a fifth unit appears to be in use. GMDA did not issue a separate release on it that we found.

What this means by area

  • Golf Course Extension Road, Sohna Road and the SPR (Sectors 58–80): served by the new Sector 72 boosting station, 95 MLD; see Sector 72 Boosting Station: 95 MLD for Sectors 58-80 (2026).
  • Dwarka Expressway and New Gurgaon (Sectors 81–115): the target of the sixth Chandu Budhera unit, 24 months after work is allotted; see Dwarka Expressway, Gurgaon and New Gurgaon, Gurgaon.
  • Old Gurugram: GMDA shut supply from the Sector 16 boosting station and Basai WTP for 24 hours from 23 October 2026 for upgradation work (GMDA public notice).

How to read these numbers as a buyer

  • Supply is not demand. GMDA's releases give supply and capacity, not a current demand figure, so we do not state a shortfall.
  • City totals hide tail-end areas. Ask a society how many hours of GMDA supply it gets and how often it buys tankers.
  • Dates run from approval or allotment, not from today. Track the GMDA news page for award and commissioning dates.
  • For who supplies what (GMDA master lines vs MCG and colony networks), see Gurugram Water and Sewer: GMDA vs MCG and What Buyers Should Check.