ATS has seven live housing registrations in Gurgaon on the HRERA Gurugram register, under five different promoter companies: ATS Grandstand Phase 1 and Phase 2 (Sector 99A), ATS Marigold (Sector 89A), Sanctuary 105 Phase 1 and Phase 2 and The Grove at Sanctuary (Sector 105), and ATS Triumph Villas (Sector 104). HRERA completion dates run from 28 February 2027 (Marigold) to 31 December 2031 (Sanctuary 105 Phase 2). The newest, Grandstand Phase 2, was registered on 17 August 2026 with 362 apartments.
Updated 20 November 2026. We read every ATS-linked row on the register and the REP-I filing for each project. Sanctuary 105 and Triumph Villas are registered to companies without “ATS” in the name; their filings link them to the group through the ATS Greens web domain and the ATS Tower office in Noida. No prices are shown because no official ATS price list was available to open today.
ATS projects in Gurgaon: HRERA table
Project — Sector — HRERA promoter — RERA no. — Homes (REP-I) — HRERA completion. Ordered by completion date.
- ATS Marigold — 89A — ATS Real Estate Builders Pvt Ltd — RERA-GRG-345-2019 — 422 apartments, 6 row houses — 28 Feb 2027
- The Grove at Sanctuary — 105 — 1000 Trees Housing Pvt Ltd — RERA-GRG-2143-2025 — smaller units up to about 1,135 sq ft — 30 Oct 2028
- ATS Triumph Villas — 104 — Greatvalue HPL Infratech Pvt Ltd — RERA-GRG-2073-2025 — 19 — 15 Dec 2028
- ATS Grandstand Phase 1 — 99A — ATS Realworth Pvt Ltd — RERA-GRG-379-2019 — 236 — 31 Mar 2031
- ATS Grandstand Phase 2 — 99A — Homekraft Infra Pvt Ltd — RERA-GRG-2297-2026 — 362 — 31 Mar 2031
- Sanctuary 105 (Phase 1) — 105 — 1000 Trees Housing Pvt Ltd — RERA-GRG-1634-2024 — 472 — 25 Jun 2031
- Sanctuary 105 Phase 2 — 105 — 1000 Trees Housing Pvt Ltd — RERA-GRG-1778-2024 — 262 — 31 Dec 2031
ATS Grandstand Phase 2, Sector 99A
- Promoter: Homekraft Infra Private Limited (ATS HomeKraft).
- RERA no.: RERA-GRG-2297-2026, registration GGM/1082/814/2026/54 dated 17 August 2026.
- Land: 3.568 acres.
- Homes: 362 apartments, 216 of 112.04 sq m (about 1,206 sq ft carpet) and 146 of 151.8 sq m (about 1,634 sq ft carpet).
- Estimated project cost: ₹927.73 crore; construction start 1 July 2026.
- Dates: REP-I likely completion 30 June 2031; register completion 31 March 2031. Use the register date in your agreement and ask why they differ.
- Our page: ATS Grandstand Phase 2
ATS Grandstand Phase 1, Sector 99A
- Promoter: ATS Realworth Private Limited; village Gopalpur, Sector 99A.
- RERA no.: RERA-GRG-379-2019 (interim registration 06 of 2018 dated 2 January 2018).
- Land: 2.62 acres.
- Homes: 236 apartments, 116 of 93.92 sq m (about 1,011 sq ft carpet), 116 of 103.86 sq m (about 1,118 sq ft) and 4 ground-floor homes of 128.67 sq m (about 1,385 sq ft).
- Estimated project cost: ₹190.02 crore.
- Dates: REP-I revised likely completion 27 November 2028; register completion 31 March 2031.
- Portal prices of ₹77 lakh to ₹1.57 crore and sizes of 1,550–2,850 sq ft circulate for “ATS Grandstand”. They look like older or super-area figures; rely on the filing’s carpet areas and a current, dated price sheet.
ATS Marigold, Sector 89A: possession date
- Promoter: ATS Real Estate Builders Private Limited; village Harsaru, Sector 89A.
- RERA no.: RERA-GRG-345-2019 (interim registration 55 of 2017 dated 17 August 2017).
- Land: 11.125 acres.
- Homes: 422 apartments across Towers 1 to 6: Type C of about 1,117 sq ft carpet (156), Type B of about 1,340 sq ft (156), Type A of about 1,602 sq ft (90), plus ground-floor and penthouse homes of about 2,203 to 3,569 sq ft; 6 row houses of about 4,808 sq ft; 76 EWS flats and 7 shops.
- Estimated project cost: ₹765.40 crore.
- HRERA completion: 28 February 2027.
- Sector page: Sector 89a Gurgaon, Gurgaon
Sanctuary 105, Sector 105 (ATS HomeKraft)
- Promoter: 1000 Trees Housing Private Limited, registered at ATS Tower, Noida; the filings use the ATS Greens web domain and a HomeKraft email for the authorised representative.
- Phase 1: RERA-GRG-1634-2024, registration GGM/862/594/2024/89 dated 28 August 2024; about 4.34 acres near the Daulatabad flyover; 7 towers; 472 apartments, 332 of 96.15 sq m (about 1,035 sq ft carpet) and 140 of 145.39 sq m (about 1,565 sq ft); estimated cost ₹833.95 crore; HRERA completion 25 June 2031.
- Phase 2: RERA-GRG-1778-2024, registration GGM/922/654/2025/25 dated 4 March 2025; 4.894 acres; 262 apartments, 126 of about 1,035 sq ft and 136 of about 1,565 sq ft; estimated cost ₹637.88 crore; HRERA completion 31 December 2031.
- The Grove at Sanctuary: RERA-GRG-2143-2025, registration GGM/1040/772/2026/12 dated 19 February 2026; a smaller-unit project in the same licence with carpet areas up to about 105 sq m (about 1,135 sq ft); construction start 31 October 2025; HRERA completion 30 October 2028.
- Our page: ATS Sanctuary 105. Sector page: Sector 105 Gurgaon, Gurgaon
ATS Triumph Villas, Sector 104
- Promoter: Greatvalue HPL Infratech Private Limited; the filing uses the ATS Greens domain and the ATS Tower office.
- RERA no.: RERA-GRG-2073-2025, registration GGM/1051/783/2026/23 dated 20 March 2026.
- Land: 1.63 acres within a 14.093-acre licence in village Dhanwapur.
- Homes: 19 large homes, 4 of 451.97 sq m and 15 of 458.93 sq m carpet (about 4,865 to 4,940 sq ft), each counted as its own building.
- Estimated project cost: ₹142.35 crore; construction start 1 January 2026.
- HRERA completion: 15 December 2028.
- Our page: ATS Triumph Villas. Sector page: Sector 104 Gurgaon, Gurgaon
Why are ATS projects under different company names?
Real estate groups often register each project in a separate company or LLP that holds that land. For ATS in Gurgaon the HRERA promoters are ATS Realworth (Grandstand Phase 1), Homekraft Infra (Grandstand Phase 2), ATS Real Estate Builders (Marigold), 1000 Trees Housing (Sanctuary 105, The Grove) and Greatvalue HPL Infratech (Triumph Villas). This is normal; what matters is that the company on your allotment letter and payment account is the same as the HRERA promoter for that phase.
How to check an ATS project on HRERA
- Search the HRERA Gurugram list by project name: “ATS GRANDSTAND”, “ATS MARIGOLD”, “ATS TRIUMPH VILLAS”, “SANCTUARY 105” and “THE GROVE AT SANCTUARY”.
- For Grandstand, check which phase your tower is in; Phase 1 and Phase 2 have different promoters and RERA numbers.
- Read the REP-I for carpet areas, then the quarterly progress reports for construction status.
- Step-by-step guide: How to Check if a Project is RERA Registered in Gurgaon (Haryana RERA Guide 2026). Sector 99A guide: Sector 99a Gurgaon, Gurgaon and Sector 99A Gurgaon: Buyer's Guide 2026 — Prices, Projects and Connectivity
Other registered projects in Sector 99A
- Spiti Homes (RERA-GRG-1541-2024; 28 July 2028) and Spiti Greenwood Estate (RERA-GRG-1569-2024; 23 August 2028), both by Spiti Township LLP.
- Green Bhoomi plots (RERA-GRG-1211-2022; 25 January 2027). BST Green Bhoomi
- Corridor: Dwarka Expressway and /new-launches