Before work starts on GMDA's two approved flyovers, the published delay figures are these: a traffic police survey found an average wait of 15 minutes at Ambedkar Chowk on Sohna Road (The Tribune, 6 May 2024), a later survey put peak waits above 10 minutes (Swarajya, 22 November 2025), and the junction carries about 6,100 passenger car units (PCU) at peak hour. Dadi Sati Chowk, between Sectors 85/86 and 89/90, handles about 9,400 PCU a day and is expected to pass 10,000 (Swarajya, 2 August 2025).

Updated 8 November 2026. On 3 November 2026 a committee chaired by Chief Minister Nayab Singh Saini approved a ₹36.36 crore flyover at Ambedkar Chowk and a ₹43.05 crore flyover at Dadi Sati Chowk, each to be finished within 18 months of the tender award (GKToday, 3 November 2026). No award has been reported yet. The approval itself, with the Millennium City Centre underpass, is covered in Millennium City Centre Underpass: ₹57 Cr Plan (Nov 2026).

Junction delay data before the flyovers

  • Ambedkar Chowk, average wait: 15 minutes, traffic police survey (The Tribune, 6 May 2024).
  • Ambedkar Chowk, peak waits: more than 10 minutes, survey cited by Swarajya (22 November 2025).
  • Ambedkar Chowk, volume: about 6,100 PCU at peak hour (Swarajya, 2 August 2025).
  • Dadi Sati Chowk, volume: about 9,400 PCU a day, expected to cross 10,000 (Swarajya, 2 August 2025); traffic there had 'trebled' (The Tribune, 6 May 2024).
  • A PCU weights vehicles by size: a car counts as one, a bus or truck as more. Peak-hour and daily counts are different measures and should not be compared directly.

What was approved on 3 November 2026

  • Ambedkar Chowk flyover: ₹36.36 crore; about 930 m; four lanes; over the Vikas Marg junction between Sectors 45–46 and 51–52; two U-turns.
  • Dadi Sati Chowk flyover: ₹43.05 crore; about 840 m; six lanes; between Sectors 85–86 and 89–90; a 7.5 m U-turn.
  • Both: built by GMDA, due within 18 months of the tender award (GKToday, 3 November 2026).

How the plans changed, 2024–2026

Use the November 2026 figures; they are the latest. Lane counts differ between reports partly because some count lanes in both directions and some in one.

  • May 2024: GMDA plans flyovers at both junctions after the traffic police survey (The Tribune, 6 May 2024).
  • August 2025: Ambedkar Chowk about 700 m and ₹52 crore; both flyovers 11 m wide, three lanes each way (Swarajya, 2 August 2025).
  • November 2025: Ambedkar about ₹52 crore and Dadi Sati about ₹59 crore, ₹111 crore together (Swarajya, 22 November 2025).
  • April 2026: Dadi Sati tender expected within a week, at about ₹40 crore (The Tribune, 22 April 2026).
  • May 2026: Ambedkar tender at about ₹32 crore for a 900 m four-lane flyover (The Tribune, 8 May 2026).
  • July 2026: after locals sought an underpass as well, tenders were reissued for six-lane designs: Ambedkar about 700 m at ₹35.89 crore, Dadi Sati about 840 m at ₹44.39 crore; the traffic study found no underpass needed for now (Amar Ujala, 5 July 2026).
  • November 2026: approved at ₹36.36 crore (930 m, four lanes) and ₹43.05 crore (840 m, six lanes) (GKToday, 3 November 2026).

When could the flyovers open?

Not before an award. The approval sets 18 months from the tender award; GMDA has not announced an award date. If awards came in early 2027, 18 months would point to the second half of 2028. That is our arithmetic, not a GMDA date. Expect diversions at both junctions while work is under way.

Registered homes within 1.5 km

Active residential HARERA registrations whose sector centre is within 1.5 km of the junction (Dadi Sati Chowk placed at the midpoint of Sectors 85, 86, 89 and 90). Registered completion dates in brackets.

  • Ambedkar Chowk: The Dualis, Sector 46, GGM/939/671/2025/42 (31 Dec 2031); Orchid Ivy, Sector 51, GGM/597/329/2022/72, and Orchid Ivy-2, GGM/646/378/2022/121 (31 Dec 2026).
  • Dadi Sati Chowk, within about 1 km: SS Camasa, Sector 90, GGM/881/613/2024/108 (30 Sep 2031) — SS Camasa; SS Whitewater, Sector 90, GGM/781/513/2024/08 (14 Sep 2028); MRG Primark, Sector 90, GGM/738/470/2023/82 (31 Jul 2027); Anantam, Sector 85, GGM/829/561/2024/56 (21 Oct 2028) — Ganga Anantam; SS Linden IV, Sector 85, GGM/731/463/2023/75 (28 Feb 2028); Godrej Air Phases I–IV, Sector 85, GGM/300/2018/32 to GGM/303/2018/35 (2027) — Godrej Air.
  • Dadi Sati Chowk, 1.1–1.3 km: Serenity Hills Phases 1 and 2, Sector 86, GGM/993/725/2025/96 and /97 (30 Sep 2032) — Emaar Serenity Hills; Godrej Zenith, Sector 89, GGM/799/531/2024/26 (31 Mar 2031) — Godrej Zenith; M3M Soulitude Central, Sector 89, GGM/1041/773/2026/13 (31 Jul 2030).