On-time record · Karnataka RERA · October 2026
Sattva (Salarpuria) delivers on time
Karnataka RERA records (checked October 2026) show Sattva (Salarpuria) delivered 8 of 10 certified Bengaluru projects (80%) by the date promised at registration, allowing for the COVID-19 extension. That puts it on Property Point's list of Bengaluru builders who deliver on time.
- Delivered on time
- 80%
- Projects on time
- 8 of 10
- Bengaluru registrations
- 31
Delivered as promised
8 Sattva (Salarpuria) projects finished on time
| Project | Area | Promised by | Certificate | Record |
|---|---|---|---|---|
| Sattva Bliss | Bengaluru East | Aug 2027 | Jun 2025 | K-RERA |
| SALARPURIA-SATTVA ANUGRAHA | Bengaluru North | Dec 2024 | Jun 2024 | K-RERA |
| SALARPURIA-SATTVA SIGNET | Bengaluru East | Aug 2024 | May 2024 | K-RERA |
| SALARPURIA-SATTVA EXOTIC | Bengaluru North | Aug 2024 | Apr 2024 | K-RERA |
| SALARPURIA-SATTVA ANUGRAHA | Bengaluru North | Mar 2022 | Apr 2021 | K-RERA |
| DIVINITY, a project jointly promoted by Salarpuria and Sattva Group | Bengaluru South | Mar 2022 | Mar 2020 | K-RERA |
| SALARPURIA-SATTVA EAST CREST | Bengaluru East | Jun 2021 | Mar 2019 | K-RERA |
| SALARPURIA-SATTVA CADENZA | Bengaluru South | Jun 2019 | Dec 2018 | K-RERA |
“Promised by” is the completion date declared to K-RERA plus the COVID-19 extension; “Certificate” is the first occupancy or completion certificate on the project's K-RERA page.