The Tumakuru metro is a PROPOSED extension of the Green Line from Madavara to Tumakuru. Its detailed project report (DPR) was handed to Home Minister G Parameshwara on 23 May 2026: 59.6 km, 27 elevated stations, an estimated ₹20,649 crore, under a public-private partnership (IANS via The News Minute, 24 May 2026). The DPR was to go to the state Cabinet; we found no Cabinet decision, cost sanction or start date as of 8 November 2026.

Updated 8 November 2026. We re-checked the line's history from the 2025 feasibility decision to its listing in the proposed Phase 4 on 27 October 2026, and looked at what Tumakuru Road has today: the Green Line ending at Madavara and K-RERA projects near it. Area guide: Tumkur Road and Nagasandra, Bengaluru: Buyer's Guide 2026 — Prices, Metro, Projects and Risks.

Tumakuru metro at a glance

  • Route — Madavara (Green Line terminus) to Tumakuru along Tumakuru Road (NH-48) via Nelamangala (OneIndia, 27 Oct 2026).
  • Length — 59.6 km in the DPR report (The News Minute, 24 May 2026); 59.9 km in the Phase 4 report (OneIndia, 27 Oct 2026).
  • Stations — 27 elevated stations (The News Minute, 24 May 2026). No station names have been published.
  • Cost — ₹20,649 crore estimate (The News Minute, 24 May 2026; Swarajya, 30 Sep 2025, for the first phase).
  • Model — public-private partnership (The News Minute, 24 May 2026).
  • DPR consultant — Aarvee Engineering Consultants, which also did the feasibility work (The News Minute, 24 May 2026).
  • Stage — DPR complete; awaiting a Cabinet decision. Listed under the proposed Phase 4, which BMRCL says is not finalised (GoodReturns citing Moneycontrol, 27 Oct 2026).

Timeline: from budget line to DPR

  • 2024-25 state Budget — Chief Minister Siddaramaiah announced the project (Swarajya, 30 Sep 2025).
  • 25 Sep 2025 — government order directing BMRCL to prepare a fresh DPR, costing ₹3 crore (Swarajya, 30 Sep 2025).
  • 29 Sep 2025 — Home Minister G Parameshwara confirmed the government had accepted the feasibility study (Swarajya, 30 Sep 2025).
  • 23 May 2026 — DPR received at Vidhana Soudha, with the Chief Secretary and senior BMRCL officials present (The News Minute, 24 May 2026).
  • 27 Oct 2026 — listed first among eight proposed Phase 4 corridors (OneIndia, 27 Oct 2026).
  • Next — state Cabinet decision, then approvals, tendering and construction, in that order (The News Minute, 24 May 2026).

What is NOT decided

The Cabinet has not cleared the DPR as far as we could find. No station list, alignment drawing, private partner or land notice has been published. Because it is planned as a PPP, the line also depends on finding a partner willing to bid. A brochure that names a 'Tumakuru metro station' near a project is quoting something that does not yet exist officially.

What Tumakuru Road has today

The Green Line runs to Madavara, its northern end, and the Nagasandra–Madavara extension opened on 7 November 2024 (our station file, citing Wikipedia and The News Minute). Beyond Madavara the commute is by road on NH-48. Our catalogue has few K-RERA listings past Madavara, so the list is short; distances are straight lines from our pin to the nearest open station.

  • Sattva Green Groves — Sattva Green Groves, plotted development near Nelamangala toll, K-RERA PRM/KA/RERA/1250/307/PR/040524/006863. About 11.7 km from Madavara station.
  • Brigade Lumina — Brigade Lumina, Chikkabidarakallu (Tumkur Main Road), K-RERA PRM/KA/RERA/1251/309/PR/230326/008545, 416 units, RERA completion 31 Dec 2030. Chikkabidarakallu has a Green Line station.
  • Prestige Jindal City — Prestige Jindal City, Tumkur Road (Bagalakunte/Anchepalya), ready to move. About 0.4 km from Chikkabidarakallu station.

What to do now

  • 1. Value a home or plot near Nelamangala or Dobbaspet on today's access: Madavara station plus NH-48. Do not pay for a metro that has no approval.
  • 2. Ask any seller who quotes a station distance for the source. The only official document is the DPR, and its station list has not been published.
  • 3. Check the K-RERA registration and completion date on rera.karnataka.gov.in before paying a booking amount.
  • 4. Landowners along NH-48: keep RTC and mutation records current. No land notice exists; when one is issued it will list survey numbers and an objection period.
  • 5. Watch for the Cabinet decision on the DPR. That is the first real milestone; we will update this page when it happens.