Under Section 14(3) of the RERA Act, 2016, a builder must repair any structural defect, or any defect in workmanship, quality or services, that you report within five years of handing over possession. The repair must be free and done within 30 days. If it is not, you are entitled to compensation. In Gurgaon you enforce this through HRERA Gurugram: a complaint costs ₹1,000 plus ₹10 per annexure.

Updated 17 November 2026. We read Section 14 of the Act, the Haryana RERA Rules 2017 (the defect definition, complaint rules, fee schedule and model agreement) and HRERA Gurugram’s complaint steps. Delay compensation is a separate topic: HRERA Delay Interest Gurugram 2026: Rate & How to Calculate.

What does RERA’s defect liability actually cover?

Section 14(3) covers more than cracks. It covers any structural defect, any other defect in workmanship, quality or provision of services, and any other obligation of the promoter under the agreement for sale, if it is brought to the promoter’s notice within five years of handover.

Haryana’s Rules define ‘structural defects’ in rule 2(u) as actual physical damage to load-bearing elements, such as faults, breakage or cracks in columns, walls, slabs and beams, that can affect strength and stability. That includes:

  • Design faults in reinforced concrete (RCC) or structural steel
  • Bad workmanship in RCC or steel work
  • Defective materials used in that work
  • Major masonry cracks caused by RCC or steel failure
  • Any defect shown to come from the promoter’s negligence, inferior materials or breach of codes

Seepage, leaking plumbing, faulty electrical work or poor finishing are not ‘structural’ under rule 2(u), but they can still fall under ‘workmanship, quality or provision of services’ in Section 14(3). The builder is not liable for defects you cause by structural or architectural changes to the original design.

Is it 30 days or 90 days in Haryana?

The Act says 30 days. Haryana’s model agreement for sale, printed as Annexure A of the Rules PDF on haryanarera.gov.in, says in clause 12 that the promoter must fix such defects ‘within ninety days’. The Act is the parent law, so cite Section 14(3) and its 30 days in your notice, and take legal advice if your agreement copies the 90-day line. Clause 12 of the model agreement also uses the five-year window from handover.

How do you notify the builder? A notice outline

  • Heading: ‘Notice under Section 14(3) of the Real Estate (Regulation and Development) Act, 2016’
  • Your name, flat number, tower, project, and HRERA registration number
  • Possession date (from the possession letter) to show you are within five years
  • Each defect: location, when first noticed, and photo or video references with dates
  • Whether it is structural (name the element: slab, beam, column) or workmanship and quality
  • Request: rectify free of charge within 30 days of this notice, and confirm a visit date in writing
  • Statement that if it is not rectified, you will seek compensation before HRERA Gurugram
  • Send by email and speed post to the promoter’s registered address; keep the tracking report

Common-area defects, such as basement seepage, façade cracks or terrace waterproofing, are better raised by the residents’ association together, with a list signed by affected owners.

What mistakes weaken a defect claim?

  • Reporting only by phone or to the site supervisor. Without a written, dated notice, the five-year and 30-day clocks are hard to prove
  • Painting over cracks or retiling before taking dated photos
  • Making structural changes, such as breaking walls or adding loads, which Haryana’s rules exclude from the builder’s liability
  • Waiting until year five. A defect reported early is easier to link to construction than to wear and tear
  • Letting a maintenance ticket close without a written note of what was repaired and why

What evidence should you keep?

  • Possession letter and conveyance deed
  • Your snag list at handover and the builder’s acknowledgement
  • Dated photos and videos, and moisture or crack-width readings if you have them
  • An independent engineer’s report for anything structural
  • All emails, ticket numbers and visit reports
  • Receipts for any emergency repair you paid for, to claim later

How do you file with HRERA Gurugram if it is not fixed?

Choose the right forum. Rule 28 covers complaints to the Authority in Form ‘CRA’ for breaches of the Act, such as ordering a repair. Rule 29 covers complaints to the adjudicating officer in Form ‘CAO’ for interest and compensation under Sections 12, 14, 18 and 19. Schedule III sets the Authority’s complaint fee at ₹1,000. HRERA Gurugram’s published steps are:

  • Read the HRERA complaint regulations, then click ‘Complaint Registration’ on the HRERA Gurugram page
  • Fill in the form; you get an online complaint number for all further correspondence
  • Pay ₹1,000 per complaint plus ₹10 per annexure, by demand draft to ‘Haryana Real Estate Regulatory Authority Gurugram’ or by the online gateway
  • Print the registration form (Performa-B) and type the detailed complaint in the format of the regulation dated 16 February 2018
  • Serve a signed copy on the builder by speed post and email; attach the tracking and email reports
  • Deliver one set plus one per respondent at the HRERA office within 30 days, with Word and PDF soft copies
  • Track status under ‘Search Complaint status’

A worked timeline (our arithmetic): possession on 1 March 2024 means the five-year window runs to 28 February 2029. A notice delivered on 10 December 2026 gives the builder until 9 January 2027 under the Act’s 30 days. If nothing is fixed by then, file with HRERA, attaching the notice and delivery proof.

Full complaint walkthrough: How to File a Haryana RERA Complaint in Gurugram: Process, Fee and Documents. If you signed the conveyance deed under protest: Signing a Conveyance Deed Under Protest: HRERA's 2026 Rulings. Track your project on New Hrera Registrations, Gurgaon; budget repairs at /calculators/gurgaon-total-cost; city hub /gurgaon.