Hero Realty's The Palatial in Sector 104, Dwarka Expressway, is registered with HRERA Gurugram in three phases: Phase 1 (Tower E) and Phase 2 (Tower D), both on 31 January 2025, and Phase 4 (Towers A and B, club and commercial) on 27 January 2025, each valid to 30 June 2030. The project was launched with 3.5 and 4.5 BHK homes at ₹4.68–6.15 crore (MGS Architecture).

Updated 10 November 2026. We opened the three HRERA REP-I filings and read the launch and February 2026 coverage. Listing pages disagree on towers and units because the project is sold in phases; this page maps each phase to its registration.

Hero The Palatial at a glance

  • Developer: Hero Realty Pvt Ltd (Hero Homes).
  • Location: Sector 104, Dwarka Expressway; villages Gurugram and Tikampur, Kadipur tehsil (HRERA REP-I).
  • Land: about 11 acres (MGS Architecture); licensed area 11.0901 acres under licences 199 of 2023 (5 October 2023) and 15 of 2024 (30 January 2024) (HRERA REP-I, Phase 4).
  • Homes: over 680 residences, 3.5 and 4.5 BHK (MGS Architecture).
  • Club and retail: 57,000 sq ft clubhouse; over 3 lakh sq ft of high-street retail (MGS Architecture).
  • Smart-home tie-up: Panasonic Electric Works India solutions in 150 homes (Construction World, 10 February 2026).

The Palatial phases and HRERA numbers

Phase — towers — HRERA number and date — land — homes — estimated cost — likely completion (REP-I) — valid to (register).

  • Phase 1 — Tower E — GGM/907/639/2025/10, 31 Jan 2025 — 1.398 acres — 170 homes — ₹631.55 crore — 31 Dec 2029 — 30 Jun 2030.
  • Phase 2 — Tower D — GGM/908/640/2025/11, 31 Jan 2025 — 1.0768 acres — 174 homes — ₹665.20 crore — 31 Dec 2029 — 30 Jun 2030.
  • Phase 4 — Towers A and B, club (community hall) and commercial — GGM/906/638/2025/09, 27 Jan 2025 — 4.6531 acres — about 254 apartments in its main groups, plus commercial units — ₹1,781.65 crore — 31 Dec 2029 — 30 Jun 2030.
  • Phase 3 — not on our copy of the HRERA Gurugram register (9 November 2026). Ask the sales office which tower it covers and when it will be registered.

What are the carpet areas at The Palatial?

From the HRERA filings; square feet are our conversion (1 sq m = 10.764 sq ft).

  • Towers E and D: 134.35 sq m (about 1,446 sq ft) — 164 homes in E and 168 in D; 118.14 sq m (about 1,272 sq ft) — 6 homes in each.
  • Towers A and B: 168.00 sq m (about 1,808 sq ft) — 236 homes; 146.35 sq m (about 1,575 sq ft) — 12 homes; 314.87 sq m (about 3,389 sq ft) — 4 homes; 617.74 sq m (about 6,649 sq ft) — 2 homes.

What is the price of Hero The Palatial?

At launch, Hero priced the 3.5 and 4.5 BHK homes from ₹4.68 crore to ₹6.15 crore (MGS Architecture). In February 2026, Construction World reported prices starting from ₹5.25 crore for the 3.5 and 4.5 BHK homes (10 February 2026). A broker listing gives super areas of about 2,833 and 3,457 sq ft (JLL Homes, portal, approx). Ask for the current price sheet for your tower, since phases can be priced differently.

When is possession of Hero The Palatial?

Each REP-I filing gives construction start as 1 January 2025 and likely completion as 31 December 2029; the register shows each registration valid to 30 June 2030. Possession follows completion and the occupation certificate.

  • 5 October 2023 and 30 January 2024 — licences 199 of 2023 and 15 of 2024 (HRERA REP-I).
  • 1 January 2025 — likely construction start for all three registered phases (HRERA REP-I).
  • 27 and 31 January 2025 — Phase 4, Phase 1 and Phase 2 registered (HRERA register).
  • 10 February 2026 — Panasonic smart-home tie-up for 150 homes announced (Construction World).
  • 31 December 2029 — likely completion; registrations valid to 30 June 2030.

What amenities does The Palatial offer?

The launch coverage lists a 57,000 sq ft clubhouse with a double-height entrance, banquet hall and fine-dining restaurant, a temperature-controlled pool, fitness centre and wellness zones, spa and salon, badminton and squash courts, rooms for music, dance and aerobics, and a business centre with work-from-home zones. Homes come with digital automation and smart security, a choice of 13 interior palettes, EV charging and Wi-Fi in common areas (MGS Architecture). Over 3 lakh sq ft of high-street retail is part of the plan; Phase 4's registration includes the commercial component.

Sector 104 neighbours

  • Delphine, Central Park — Phases I–III registered 16 Oct 2025 — valid to Aug–Nov 2032 — studios ₹3–5 crore, 3 BHK from ₹11 crore (builder statement, NBM&CW, 25 Nov 2025) — Central Park Delphine.
  • ATS Triumph Villas — GGM/1051/783/2026/23 (20 Mar 2026) — valid to 15 Dec 2028.
  • BPTP Amstoria Verti-Greens — Sector 102 — GGM/910/642/2025/13 (5 Feb 2025) — valid to 14 Dec 2031 — BPTP Amstoria Verti-Greens.

Which fits whom?

  • 3.5 BHK buyers on Dwarka Expressway who want a 2029–2030 registered date: Towers E and D.
  • Buyers who want the larger 4.5 BHK and the tower next to the club: Towers A and B (Phase 4).
  • Buyers weighing 3 vs 4 BHK on the corridor: Dwarka Expressway 3 BHK vs 4 BHK: 37% Price Gap (2026).

What to check before you pay

  • The phase and tower of your unit, and the matching HRERA number.
  • The carpet area from the table above against the super area on the price sheet.
  • The completion date in your agreement (the filings say 31 December 2029; registrations run to 30 June 2030).
  • The cost of club membership, parking and any smart-home package.