In 2026, Gurugram's agencies approved or tendered at least eight flyovers, underpasses and elevated roads. The largest is the ₹776 crore, 4.23 km elevated corridor on the Southern Peripheral Road (SPR) from NH-48 to Vatika Chowk, with bids due on 18 November 2026. Haryana also cleared the 2.25 km Hero Honda Chowk-Umang Bhardwaj Chowk elevated road on 1 October. GMDA has tendered flyovers at Ambedkar Chowk and Dadi Sati Chowk, and NHAI has given in-principle approval to a Shankar Chowk flyover and a Moulsari Avenue underpass.
Updated 3 November 2026. Ranking pages cover one junction each. This list puts them in one place, by stage: approved, tendered or proposed. Each item gives the cost, length and the sectors it serves, with the date of the report.
Which flyovers and underpasses were approved in Gurgaon in 2026?
- SPR elevated corridor, NH-48 to Vatika Chowk — GMDA — 4.23 km with interchanges, loops and ramps — ₹776 crore excluding GST — EPC tender opened 1 October 2026, bids due 18 November 2026, 30-month build plus 10 years of maintenance (Construction World, 9 October 2026).
- Hero Honda Chowk to Umang Bhardwaj Chowk elevated road — GMDA — 2.25 km — last published estimate ₹181 crore — approved by Haryana, announced 1 October 2026; fresh DPR next (Swarajya, 2 October 2026).
- Shankar Chowk flyover and Moulsari Avenue underpass — built and funded by DLF under NHAI's in-principle approval — three-lane flyover from Ambience Mall towards Cyber City and three-lane underpass from Moulsari Avenue towards Delhi under NH-48 — about ₹130 to ₹140 crore for both, per a company official (Construction World, 8 October 2026).
- Ambedkar Chowk flyover, Sectors 45/46 to 51/52 — GMDA — tendered (see the two published versions below).
- Dadi Sati Chowk flyover, Sectors 85/86 to 89/90 — GMDA — about 840 m, six lanes, about ₹44.39 crore — board-approved and tendered; target two years (Amar Ujala, 5 July 2026).
- Underpass near Z Chowk, opposite Millennium City Centre metro station — GMDA — part of the IFFCO Chowk-SPR corridor approval of 27 August 2026; GMDA's board has approved it (Construction World; Amar Ujala).
- Global City trumpet interchange on the Dwarka Expressway, near the Pataudi Road junction — NHAI to build, HSIIDC to fund — four-lane underground interchange with about 3.2 km of ramps — about ₹923 crore — cleared; work expected to take about 30 months (Swarajya, 7 March 2026).
What did Haryana approve on 27 August 2026?
Haryana's high-powered works purchase committee, chaired by Chief Minister Nayab Singh Saini in Chandigarh, approved two GMDA projects worth ₹68.69 crore in all (Construction World).
- IFFCO Chowk-SPR corridor (₹41.86 crore): rebuilding 7.1 km of main carriageway along the sector-dividing roads of Sectors 28/29, 43/44, 52/52A and 56/57, with footpaths, cycle tracks, drains and junction upgrades, plus an underpass near Z Chowk. Target: within one year.
- Sector 68-69 missing link (₹26.83 crore): 900 m of new carriageway, 1,100 m of overlay and nearly 2 km of new two-lane service road, connecting the SPR and Sohna Road. It serves Sectors 68, 69, 70, 70A, 75 and 76.
What is the Ambedkar Chowk flyover on Sohna Road?
Ambedkar Chowk joins Sectors 45, 46, 51 and 52, and links Ardee City and Sohna Road. Two versions have been published in 2026:
- May 2026: GMDA floated a tender for a 900 m four-lane flyover with four-lane service roads, at about ₹32 crore, with completion targeted two years after work starts (The Tribune, 8 May 2026).
- July 2026: after a traffic study, GMDA issued tenders for a six-lane flyover of about 700 m at about ₹35.89 crore, with two-lane service roads, noise barriers and space left for a future underpass. Target: two years (Amar Ujala, 5 July 2026).
Our reading: the July version is the later one, so use it. Check GMDA's tender page for the award before relying on either number.
Which projects are still proposals?
- Three flyovers along Netaji Subhash Marg at the Sector 44-45, 30-41 and 45-46 crossings, along the planned metro line from Millennium City Centre to Bakhtawar Chowk. GMDA asked GMRL to study them, and feasibility studies come first (Prop News Time, 3 June 2026).
- GMDA's ₹386 crore plan for 51 road projects, including five elevated corridors and seven flyovers or underpasses. It names four routes: NH-48 to Vatika Chowk, Rajiv Chowk to Atul Kataria Chowk, Mahavir Chowk to IFFCO Chowk, and Atul Kataria Chowk to Dwarka Expressway (The Tribune via Newswav, 28 May 2026). The first of these is now out to tender as the SPR elevated corridor.
- Bakhtawar Chowk: covered in Bakhtawar Chowk Flyover Gurugram: Double-Decker Metro Plan 2026.
What are the SPR underpasses and flyovers?
On the SPR, the main 2026 item is the 4.23 km elevated corridor between NH-48 and Vatika Chowk (Package 1, km 0 to km 4.23). It includes interchanges, loops and ramps, so through traffic can stay above the junctions. Tender ID 2026_HRY_551863_1 closes on 18 November 2026. The Sector 68-69 link gives SPR and Sohna Road a second connection near Sectors 68 to 70A. The full tender story is in SPR Gurgaon News: ₹776 Crore Elevated Road Tender, Explained.
On the SPR's north side, the IFFCO Chowk-SPR upgrade rebuilds the sector-dividing road from IFFCO Chowk down to the SPR. These three works together change how Golf Course Extension Road and SPR sectors reach NH-48 and central Gurugram.
Which flyover will help Dwarka Expressway and New Gurgaon?
- Hero Honda Chowk-Umang Bhardwaj Chowk elevated road: links NH-48 and the southern end of the Dwarka Expressway. Details: Hero Honda Chowk to Umang Bhardwaj Chowk Elevated Road.
- Global City trumpet interchange: grade-separated access from the Expressway to Global City (Sectors 36, 36B, 37 and 37B, over 1,003 acres) and Vision City (Sector 88, 121 acres), with a loop ramp for traffic from Manesar (Swarajya, 7 March 2026).
- Dadi Sati Chowk flyover: between Sectors 85/86 and 89/90, meant to ease trips between the Dwarka Expressway and Manesar (Amar Ujala).
What happens next on these projects?
- 18 November 2026: bids close for the SPR elevated corridor, NH-48 to Vatika Chowk (tender 2026_HRY_551863_1). The award will start the 30-month build clock.
- Hero Honda Chowk-Umang Bhardwaj Chowk: GMDA is appointing a consultant for a fresh DPR. Length, lanes and cost will be fixed in it, and a construction tender follows.
- Ambedkar Chowk and Dadi Sati Chowk: tenders issued; GMDA's target is two years for each once work starts. Watch for the work award.
- IFFCO Chowk-SPR corridor and Sector 68-69 link: approved on 27 August 2026 and moving to tendering, with the corridor targeted within one year.
- Shankar Chowk and Moulsari Avenue: DLF must deposit charges, submit engineering, traffic, structural, drainage and road-safety documents, and get a traffic management plan approved before each construction stage (Construction World, 8 October 2026).
- Global City interchange: NHAI said execution details were being worked out in March 2026, with about 30 months of work expected.
How do these projects affect home buyers?
A tender or an approval is a step, not an opening date. Before you pay for 'connectivity', check three things: which stage the project is at (proposal, approved, tendered or awarded), the build period in the tender, and which junction you will actually cross every day. For a project you are considering, map your daily route and see which of the works above is on it.
These registered projects sit near the SPR and Golf Course Extension Road works:
- Smartworld Sky Arc — Sector 69 — price on request (no developer price published) — completion May 2032 — HARERA GGM/878/610/2024/105. See Smartworld Sky Arc
- Tulip Violet, Towers A9 and A10 — Sector 69 — price on request — completion Dec 2032 — HARERA GGM/967/699/2025/70. See Tulip Violet
- Signature Global Cloverdale SPR — Sector 71 — price on request; the developer said ₹4 to ₹7 Cr a home in June 2025 — completion May 2031 — HARERA GGM/955/687/2025/58. See Signature Global Cloverdale SPR
- M3M Opus — Sector 67 — approx ₹5.2 to ₹5.3 Cr for a 3 BHK (dated listings; our listing, checked October 2026) — completion Nov 2029 — HARERA GGM/876/608/2024/103. See M3M Opus
Area pages: Southern Peripheral Road, Gurgaon and Golf Course Extension Road, Gurgaon. Sector guide: Sector 69 Gurgaon (Southern Peripheral Road): Buyer's Guide 2026 — Prices, Projects, Connectivity.