In a Gurgaon builder floor, the terrace belongs to all floor owners in common unless your deed says otherwise. Haryana’s 2009 floor-registration policies list ‘common roofs’, staircases, parking areas and the land under the building as common areas that ‘shall remain un-divided’. Each floor owner gets an equal share of the land (25% each where there are four floors). Exclusive use of the terrace or a named parking slot is possible only if it is written into the floor-wise declaration and your sale deed.
Updated 17 November 2026. We read the 2009 instructions on independent floors for licensed colonies and HSVP sectors, the 2019 land-share policy, the S+4 memo of 2 July 2024 and the parking and FAR rules of the Haryana Building Code (amended to 13 August 2026). This is a general explainer, not legal advice.
Who owns the terrace in a builder floor?
Both 2009 policies define common areas to include ‘the land covered by the building’, ‘common roofs, corridors, staircase’, parking areas, passages, tanks, pumps and lifts. The HSVP version adds that common areas may be used by all owners ‘equally and without hindrance’, and that restricted common areas may be specified for the use of some floors only. So a top-floor owner’s exclusive terrace is a restricted common area that must be declared; it is not automatic.
Also note what a terrace right cannot do. The Code caps a plot at four homes and 16.5 m, and the policies say registration brings ‘no increase in maximum permissible FAR’. A right to build on the roof is worth little on a plot already at its limit, and Gurgaon is not approving new S+4 floors now.
How is land share split among floor owners?
The 7 March 2019 policy fixes equal shares of land cost: 50% each for two floors, one third each for three and 25% each for four. All owners jointly own the full plot, and no fragmentation is allowed. The HSVP policy adds that each owner’s percentage share in common areas is ‘of a permanent character’ and cannot change without the written consent of all owners. Enhanced land compensation and extension fees can be shared by a joint affidavit.
Who gets the stilt parking and the basement?
- Parking is sized per floor: on a 100–250 sq m plot the Code needs 1 car space per floor, 1.5 on 250–500 sq m and 2 above 500 sq m, in the stilt or open space within the plot
- Each owner must park inside the plot, not on the road, under the 2009 policies
- The stilt must stay open. The 2024 memo says plan approval and OC are ‘deemed to be withdrawn’ if it is enclosed
- A guard room and toilet (16 sq m on plots up to 200 sq m, 20 sq m above) may sit in the stilt, counted in FAR
- A basement belongs to the ground floor unless all owners agree to hold it in common
- In HSVP plots, a garage, servant quarter or store built at ground level forms part of the ground floor
What should the deed say? A clause checklist
Ask your lawyer to check that the sale deed and the floor schedule cover each of these points:
- Your undivided land share as a percentage (for example 25%)
- A schedule of common areas: land, roof, staircase, lift, stilt, water tanks, pumps, meters
- Any restricted common area: who may use the terrace, and whether it is use only or a right to build
- Parking slot number(s) in the stilt, marked on the sanctioned plan
- Basement: part of the ground floor or held in common
- Lift, staircase and roof waterproofing upkeep: how costs are shared and who decides repairs
- Water tank and solar panel space on the roof for each floor
- No owner to enclose the stilt or build beyond the sanctioned plan
- How disputes will be resolved (mediation, then court)
How are disputes between floor owners resolved?
The 2009 policies say disputes are ‘limited to the agreement partners’, and the planning department or HSVP will not be a party, so most terrace and parking disputes go to civil court on the strength of the deed. One exception: for S+4 buildings, the 2024 memo set up grievance committees (chaired by the District Town Planner or the HSVP Estate Officer) for complaints about structural damage and infrastructure, with a 15-day disposal target. That is why a clear deed matters more than a verbal promise.
For the wider choice between formats, read Builder Floor or Apartment in Gurgaon? How to Decide in 2026 and Is a Builder Floor Legal in Gurgaon? 2026 Checklist. Registration steps and duty are in Builder Floor Registry in Gurgaon: Floor-Wise Registration 2026. Developer floor projects with HRERA registration include Independent Floors at DLF Alameda, Sector 73 (GGM/491/223/2021/59): Independent Floors At DLF Alameda, Sec 73. Check rates at Gurgaon and sectors at Sectors, Gurgaon.